pprroojjeecctt ffeeaassiibbiilliittyy...

51
P P R R O O J J E E C C T T F F E E A A S S I I B B I I L L I I T T Y Y R R E E P P O O R R T T Expansion of M/s Atibir Industries Co. Ltd. Existing 4 x 100 TPD Sponge Iron and addition of 15 MVA Submerged Arc Furnace for Ferro Alloys, along with 20 MW Captive Power Plant At Village: Manjhiladih, PO- Gadi Srirampur, PS- Giridih(M), District- Giridih, State- Jharkhand Applicant: M/s Atibir Industries Co. Ltd. Reg. Office: 20B, Abdul Hamid Street, 7th floor, Kolkata-700069, West Bengal

Upload: others

Post on 09-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Expansion of M/s Atibir Industries Co. Ltd.

Existing 4 x 100 TPD Sponge Iron and addition of 15

MVA Submerged Arc Furnace for Ferro Alloys,

along with 20 MW Captive Power Plant

AAtt

VViillllaaggee:: MMaannjjhhiillaaddiihh,, PPOO-- GGaaddii SSrriirraammppuurr,,

PPSS-- GGiirriiddiihh((MM)),, DDiissttrriicctt-- GGiirriiddiihh,, SSttaattee-- JJhhaarrkkhhaanndd

AApppplliiccaanntt::

M/s Atibir Industries Co. Ltd. Reg. Office: 20B, Abdul Hamid Street, 7th floor,

Kolkata-700069, West Bengal

Page 2: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER 1:

EXECUTIVE SUMMARY

1 Name of the Company M/s Atibir Industries Co. Ltd.

2

Registered Office Factory

20B Abdul Hamid Street, 7th floor, Kolkata-700069 (WB) Village: Manjhiladih, PO- Gadi Srirampur, District- Giridih, State Jharkhand

3 Name of the Directors Mr. Sandeep Kumar Sarawgi Mr. Samir Kumar Sarawgi Mr. Paras Kumar Sarawgi

4 Present Business Sponge Iron

5 Area of plant Existing 6.07 ha, addition 5.12 ha Total: 11.19 ha

6 Topo Sheet No 72 L/8 (G45U8)

7 Latitude 24° 07’ 01.62” N

8 Longitude 86° 21’ 10.60” E

9 Existing DRI (Sponge Iron 4 x 100 TPD) – 120000 TPA

10 Proposed addition

SAF (Ferro Alloys) SiMn 24750 TPA; FeMn 35640

TPA; FeSi 13860 TPA or Product Mix.

Captive Power Plant (WHRB+AFBC) - 20 MW

11 Cost of Project Existing – 35.56 crores

Proposed – 105. crores

12 Manpower requirement Total – 400 Nos.

(Existing – 250 Nos + Proposed – 150 Nos)

13 Power requirement

Existing – 1.350 MW

Expansion – 16.5 MW

Total – 18 MW

14 DG sets 500 KVA existing. Addition 3 x 500 KVA

Page 3: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

COST OF PROJECT: Total Project

SL No Details Rs. In Crores

EXISTING

Rs. In Crores

PROPOSED

1 Land & Site development incl. Boundary 0.83 3.00

2 Office Building, Infrastructure, Shed Civil

etc. 4.29 15.00

3 Plant & Machinery (incl. Pollution Control) 30.44 80.00

4 Contingencies - 7.00

Total ( as on 31.3.2018 from B/Sheet) 35.56 105.00

The company proposes for expansion to set up a 15 MVA Submerged Arc Furnace with capacity

400 TPD through the existing Sponge Iron with 20 MW Captive Power Plant, After reviewing the

various probable options including economic viability, power balancing, implementation

schedule, it was concluded that the above set up would be best suited for the project.

1.1 SELECTION OF PROCESS ROUTE

The present facilities of the plant are:

Sponge Iron Plant - having four (4) Nos. Coal Based Rotary Kilns each of 100 TPD capacity, with

an annual capacity of 120,000 Metric Tons. Sponge Iron Plant has its own material storage and

handling facilities and other auxiliary plant units.

After expansion, the following configuration is proposed for the Steel and Power Plant.

Submerged Arc Furnace

Submerged Arc Furnace with carbon electrodes will be used for manufacturing of various Ferro

alloys such as Ferro manganese, Ferro silicon and Silico Manganese or product mix.

Power Plant

The power is proposed to be produced in the most cost effective manner. The steam shall be

produced in four (4) nos. Waste Heat Recovery Boilers (WHRBs) utilizing the sensible heat of

waste gases of Sponge Iron Kilns. Each WHRB shall produce 9 to 10 t of steam and shall

comprise an evaporator, super-heaters & economizer to recover the sensible heat of kiln gases

by cooling them from 850-9000C to 1800C. Steam generated from each WHRB can generate

about 2 MW of power.

The balance requirement of steam to produce total 20 MW of power is proposed to be met by

installation of an Atmospheric Fluidized Bed Combustion (AFBC) Boiler which shall use Char &

Low C.V. Coal in the ratio of 35% & 55%.

Page 4: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Selection of Steam pressure and temperature at 66 Ata & 4900C respectively is optimum

considering high efficiency and capital cost investment and maintenance cost for the proposed

size of 20 MW for the Power Plant. T.G. Set of modern features and controls is proposed to be

inst.

1.3 CONFIGURATION AFTER EXPANSION:

4 x 100 TPD Sponge Iron Plant (Existing)

20 MW Power Plant using WHRB and AFBC boiler

and 15 MVA submerged Arc Furnace for Ferro Alloys

The proposal has been made with the following assumptions:

Total number of working days for all the units is 300 for DRI Kiln & 330 days for Ferro

Alloys Section per annum and output 100% efficiency in year of operations henceforth.

Power Plants will generate 20 MW out of which 8 MW with steam from Waste Heat

Recovery and balance 12 MW steam by using the dolochar and coal fines generated in

Sponge Iron Production.

Name of unit No. of units Capacity of

Each Unit Production Capacity

Sponge Iron (DRI) Existing 4 100 Tons 400 TPD~ 120000 TPA

Proposed – Expansion

CPP (WHRB + AFBC) WHRB - 4 x 2MW

AFBC - 1 x 12MW

8 MW

12 MW Power ~ 20 MW

SAF (Ferro Alloys) 1 15 MVA

SiMn 24750 TPA or FeMn 35640 TPA or

FeSi 13860 TPA Or product mix

Page 5: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

1.4 LICENSING/ REGISTRATION

Company has already initiated the various processes of Licensing/ Registration. Government

approvals required and status

Approval/ Consent Agency Status

License Factory Inspection

Department License No. FCA1534900201701

Land Possession Private parties &

Govt.

Existing 6.07 ha; Addition 5.12 ha

Total 11.19 ha (27.65 acres)

Environmental

Clearance

Ministry of

Environment &

Forests

For Existing: EC not required as it was established

before 2006. Project cost 35.56 crores

For Expansion: Will be obtained prior to

construction of the plant - Applied

Consent to

Establish/Operate

State Pollution

control Board

For Existing: Consent to Operate Obtained Vide

Letter No. JSPCB/HO/RNC/CTO-1038396/2017/177

Dated- 01.03.2017, valid up to 31.12.2018

For Expansion: Will be obtained prior to

construction of the plant after EC.

Power Requirement Damodar Valley

Corporation

Power requirement through DVC & Captive Power

Plant

Page 6: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER – 2

INTRODUCTION - PROFILE OF INDUSTRY

Steel is crucial to the material development of any modern economy. It is a product of a large

technologically complex industry having strong forward and backward linkages in terms of

material flow and income generation. All major economies are not only characterized by

existence of a strong steel industry, the growths of many of these economies have been largely

shaped by the strength of their steel industries during their early stages of development. Some

of the rapidly expanding newly industrialized countries like South Korea, China, and Brazil

amongst others have built up substantial capacities not only to support their rapidly growing

domestic economies, but also to export significantly to mark their presence in international

markets.

India has seen nearly a century of steel making as it stands on the threshold of a new era. The

face of Indian Iron and Steel Industry is changing at such a fast pace that it is difficult to focus it

now in the historical perspective. Steel is a core industry and thus its demand is strongly linked

to overall level of economic activity in the country. Given the inherent long-term potential of

the Indian Economy and its cyclical nature, the long-term prospects of the steel industry are

fairly comfortable. Liberalization and opening up of economy has given a new vitality to this

sector. Demand and production have been growing at a healthy rate for past two years and

forecast for next ten years is very bright. As the process of economic development takes off

growth rate in industrial and infrastructure sectors such as capital goods, power, transport,

telecommunication and hydrocarbons also increases leading to increased steel consumption.

The electric steel industry, which initially started as a result of general steel shortage and dual

pricing policy in the country in the past, has grown significantly in the recent years. The older

units have been modernizing while new units have been set up with latest technology enabling

reduction in cost of production. The major factors contributing to the existence and growth of

the industry are as follows:

Lower investment cost and shorter gestation period as compared to BF-BOF route of steel

making.

Ability for wider dispersal.

Less strain on transport and other infrastructural facilities.

Fewer unit operations.

Non-dependence on metallurgical coke and coking coal.

Less manpower per ton of steel produced.

Short conversion time from raw material to finished products.

Lower Environmental and pollution problem.

Flexibility in production of different qualities of steel and alloy steel.

Page 7: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Besides this above factors the Induction Furnace method of manufacturing steel, allows

flexibility in the charge mix, amounts to reduced electricity consumption and decreased

refractory electrode consumption which has resulted in the manufacture of international

quality steel. Since India has rich reserves of coal, and the technology for manufacturing

sponge iron is no more new, sponge iron production seems to have a bright future.

2.1 COMPANY AND DIRECTORS’ PROFILE

M/s Atibir Industries Co. Ltd. is a public limited company carrying out business in production

of sponge iron. The Group has a long experience in industrial activities.

The company has been promoted by a group of experienced businessmen who are presently

engaged in manufacturing and trading business of various products.

2.2 Details of Project Proponent

M/s Atibir Industries Co. Ltd.

Directors:

Mr. Sandeep Kumar Sarawgi S/o Sri Santosh Kumar Sarawgi

Mr. Samir Kumar Sarawgi S/o Sri Santosh Kumar Sarawgi

Mr. Paras Kumar Sarawgi S/o Mahabir Prasad Sarawgi.

Address:

Sarawgi Sadan Dumri Road, Giridih, Jharkhand.

SL

No Name & Designation Age Qualification Experience

1

Mr. Sandeep Kumar

Sarawgi ( Chairman –cum-

Managing Director)

48 yrs B. Com.

About 25 years in Steel Sector Sponge Iron/ MS Ingot , Pig Iron, TMT Bars, Wire & Nails etc. Shri Sarawgi has been a guiding force behind the Group and has played a key role in envisioning the various business initiatives of the Group. He has tried different initiatives. Production and other sector.

2 Mr. Samir Kumar Sarawgi

45 yrs

B. Com. MBA

(Finance)

About 20 years in in Steel Sector. He is looking after group activities involved in production, Finance and taxation matters.

3 Mr. Paras Kumar Sarawgi

59 yrs B. Com.

About 30 years in production and Marketing of Iron & steel products of the Group.

Page 8: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

2.3 COST OF EXISTING & PROPOSED PROJECT:

Existing unit of the plant – 4x100 TPD DRI, was established at the cost of Rs. 35.56 crores and

the proposed units of 15 MVA Submerged Arc Furnace for Ferro Alloys and 20 MW CPP is

estimated Rs. 105 crores. The total project cost after expansion is estimated as Rs. 140 crores.

Power will be used in-house for operation of the Submerged Arc Furnace and Sponge iron.

Present permission for power withdrawal from DVC is 1350 KVA.

2.4. LOCATION AND LAND USE BREAKUP

The area is having a very good infrastructural facility in terms of road connectivity as SH Giridih

to Dhanbad is at a distance of 0.8 Km and NH 2 at a distance of 50 Km from site, which is

located at Vill – Manjhiladih, P.O. – Gadi Srirampur, District – Giridih Jharkhand. Total Land Area

– 15 acres (6.07 ha). Proposed approximate use of Land:

SL Type of use Area (ha.) Area (acres)

1 Plant area after expansion 6.00 14.80

2 Administrative offices and other

buildings. 0.46 1.15

3 Roads and Paved Area 0.81 2.00

4 Storage and solid waste handling area 0.20 0.50

5 Green Belt & open area 3.72 9.20

Total land acquired 11.10 27.65

2.5. IMPLEMENTATION SCHEDULE OF PROPOSED EXPANSION

Based on the consideration that pre-project activities are accomplished prior to the award of

the main machinery order, an implementation period of 24 months from the date of signing /

effectiveness of the contract

2.6 CONNECTIVITY

Road

The proposed project site is located at a distance of 0.8 Km from SH-2 between Giridih and

Dhanbad at Vill – Manjhiladih, P.O. – Gadi Srirampur, District – Giridih Jharkhand.

Rail

The Nearest Railway Siding is Giridih at aerial distance of 6 Km (8.0 Km by road)

Page 9: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER – 3

BRIEF DESCRIPTION OF PROJECT

3.1 INTRODUCTION

Sponge Iron or Direct Reduced Iron, DRI as it is popularly known, is a high ferrous content

charge material and is used as a substitute for steel scrap as the primary raw material in the

Induction Furnace, during the process of manufacture of steel. It can be produced both in the

lump and pellet form and in a compact and briquetted form known as hot briquette iron.

Sponge Iron is becoming increasingly important around the world as a raw material source for

high quality steel; India being no exception. In the mid- seventies, the Department of Steel had

identified that sponge iron would play a major role in the growth of the secondary steel sector.

Apart from making the secondary steel sector less vulnerable to fluctuations in the

international scrap prices by reducing dependence on imports, increased domestic production

of sponge iron and the consequent reduction of scrap imports have led to substantial savings in

foreign exchange.

3.2 EXISTING UNIT: DRI - SPONGE IRON

Sponge iron or DRI (direct reduced iron) is the product obtained from direct reduction of iron

ore with an iron content varying from 83 to 92%. Reduction causes elimination of oxygen

leaving behind a honeycomb like porous structure which is “Spongy” in nature. Hence the name

Sponge Iron

3.2.1 PROCESS:

Selection of a suitable production process and the capacity of the production units form the

nucleus around which the basic concept of a plant is developed. While the selection of a

process takes into account factors like type of products, availability and amenability of local raw

materials, process status, specific energy consumption, level of energy required, and

environmental pollution etc., the capacity selection of major units would depend on the volume

of production, available unit sizes, economies of scale etc.

The process of manufacture of sponge iron is very simple. The percentage of oxygen

associated with iron as oxide is removed from the ore particle and the process is often

referred to as "Percentage Reduction"; whereas the percentage of iron forming a part of the

whole iron, and which exists in the metallic form, is called the degree of metallization in

sponge iron making technology. There are two well-established processes for the

manufacture of sponge iron, namely:

(a) The reformed natural gas process i.e. By the gaseous reduction of the iron ore.

(b) Coal based Rotary Kiln process- Solid reduction.

Page 10: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

The basic raw materials required for the production of the sponge iron are the ore, coal and

lime stone. The plant consists of iron and coal crushing plant for lime stone is envisaged. The

iron ore is crushed to the required size and fed to the day bins. The coal will also be sized and

screened. The different size fractions are fed to separate coal bins. The finer size is used for

blowing from the discharge end of the kiln and the coarser sized coal is fed along with the iron

ore, coal and lime stone. The sized materials are stored in day bins, from which the raw

materials are fed to the rotary kiln through the volumetric feeders at a predetermined rate. The

iron ore is pre-heated and reduced in the rotary kiln and passes to the rotary cooler where it

gets cooled. The cooled material then passes to the belt conveyor system to the product

separation system. A junction house is provided to take care of the any eventualities occurring

due to the breakdown of the product separation system. The hot gasses will be cooled in the

wet scrubber and cleaned before being let off through the chimney. Emergency stack provided

for the escape of gasses when there is break down of the waste gas treatment system. Control

room has the PLC operation from which the complete control and operation of the plant is

carried out.

The kiln can be divided process-wise into two zones

namely pre-heating zone and reduction zone. The pre-

heating zone is approximately 3.3% of the total length of

the kiln and the rest is taken as the reduction zone. The

material gets heated to the reduction temperature in the

pre-heating zone. Upto 200OC, the iron ore, coal and

limestone gets dried and all the moisture is vaporized.

Upto 800OC the iron ore gests roasted and any

carbonates in it get calcinated. In the coal the volatile

matter starts getting released. The limestone also gets

calcinated and becomes active. The iron ore, which is in

the form of hematite, get reduced to magnetite. After

this the materials enter to the reduction zone where the magnetite is reduced to wustite and

then to the metallic iron. The various stage wise reductions of iron ore is as shows below:-

3Fe2O3 + CO 2Fe3O4 + CO2

Fe3O4 + CO 3FeO + CO2

FeO + CO Fe + CO2

Thus the iron in the ore gets reduced to its metallic from. The sum total of the above

reactions is endothermic. So to carry out these reactions to completion additional source of

heat is required. This additional heat is obtained by burning the coal in the gas phase, which

transfers the heat to the bed material.

Page 11: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Coal contains sulphur in it. During the decomposition of the coal the sulphur is released in the

form of Iron sulphide. During the reduction process of iron ore the sponge iron picks up sulphur

by the following reaction:

FeO + H2S FeS + H2O

The iron sulphide (FeS) has deleterious effect in the steel making and is to be removed. So lime

stone is used to prevent the sulphur pick up by the sponge iron. The reaction occurring is

FeS + CaO + CO Fe + CaS + CO2

All the above reactions are possible only in the presence of CO. The generation of the CO is

most important reaction, which is called the Boudard reaction.

The Boudard reaction is as given below:

CO + CO2 2CO

The reaction is highly endothermic which is also reversible. The conditions favourable for the

forward reaction i.e. the generation of CO are:

1. The higher temperature favours the production of CO.

2. The concentration of the reactants has to be high so that the forward reaction occurs.

3. Low pressure favours the CO generation.

All the above reactions occur in the bed phase.

In the gas phase the following reactions occur:

CH4 + 2O2 CO2 + 2H2O

2CO + O 2CO2

C + O2 CO2

The reduction of iron ore is topo-chemical i.e. the reduction proceeds from the surface in the

core. The iron ore on partial reduction has all the different stages of the reduction. The hot

material, after the reduction is complete, is transferred to the total cooler via the transfer

chute. The cooler is 2.3 mtrs. in diameter and 22 mts. long and made up of Mild Steel sheet. It is

also inclined at 1.43O approximately and rotates at 1.4 rmp. It is driven by an AC motor. The

water is sprayed on the top of the shell which cools the material inside the cooler indirectly.

The heat from the material is extracted by the shell. In order to increase the surface area for

the heat extraction, fins are welded inside. Complete shell is covered by thin layer of water. The

heat is transferred from the shell to the water by convection. By this the material gets cooled to

80OC. and is discharged on the belt conveyor by the double pendulum valve. The double

pendulum valve acts as the seal for the prevention of the atmospheric air into the kiln cooler

system. The total kiln cooler system is kept under positive pressure of about 0.3–0.5 mbar. This

prevents the atmospheric air from getting into the system. The kiln has to be always operated

Page 12: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

on positive pressure as any leakage into the system will cause the re-oxidation of the sponge

iron thereby causing the drop in the quality of the product.

The material after the discharge from the cooler is dropped on to the cooler discharge

conveyor. A diversion chute is provided at the head end of this conveyor for diversion of the

material in case of break down in the production separation. The material is then sent to the

product separation system. In product separation system, consisting of double deck screen, the

material is screened to 0-3 mm and 3-20 mm size fractions. The oversize i.e. + 20mm obtained

is small in quantity so it is taken on the floor or diverted to the sponge iron bin. The 0-3 mm

sized fraction is called the fines and is fed to a drum type magnetic separator where the

magnetic sponge iron fines and the non-magnetic dolochar get separated and are fed to the

respective bins through the chutes and conveyor. The coarser fraction is similarly separated by

another magnetic separator and fed to respective bins. This magnetic fraction is called the

sponge iron lumps and the non-magnetic as char, which is the unburned coal.

Page 13: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

The gasses, which flow in the counter current direction of the material, go to the dust-settling

chamber where the heavier particles settle down. These particles are continuously removed by

the wet scrapper system. The gases then pass to the after burner chamber where the residual

carbon or CO are burned by the excess air available. The gases are at high temperature and

have lot of heat energy, which can be utilized for the power generation through the waste heat

recovery boiler. The hot gasses after the heat recovery boiler get cooled at 2000C. The gases are

then scrubbed and let of to the atmosphere at 800C through the chimney. Alternatively the hot

gases are quenched and scrubbed to clean all the dust in it. And then are let off to the

atmosphere through the stack.

3.2.2 Raw Materials – Sponge Iron

Item Requirement TPA Source and Transportation

a. Iron Ore 1,92,000 From mines in Jharkhand and Odisha –

by Rail rake and then by road.

b. Non Coking Coal 1,56,000 From various mines of CCL – by Rail

rake and/or road.

c. Dolomite/ Limestone 3,600 From U.P. by road

Railway sidings Bhaga at 75 Km in SE and Bokaro at 110 Km in SW.

3.3.1 PROPOSED: CAPTIVE POWER PLANT

Total power generation for the proposed power plant is taken as 20 MW using Steam Turbine

Generator set. Production of steam required for power generation is proposed from following

sources:

Installation of four (4) nos of Waste Heat Recovery Steam Generators capable of

producing 9T/h of steam each from the hot flue gases produced by existing 4 x 100T

capacity DRI Rotary Kilns.

Installation of AFBC type boiler for steam generation using waste char as fuel

supplemented by coal firing to the extent required. Capacity of the boiler is proposed as

50 T/h of steam to ensure production of 20 MW power even when three out of four

kilns are in operation.

Power Generation from Coal Based Sponge Iron Technology. Power is generated through Waste

Recovery Boiler (WHRB) & Fluidized Bed Combustion Boiler (FBC).

Page 14: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

S. No. Particulars Capacity

1. With steam from WHRB 8 MW

2. With steam from AFBC 12 MW

TOTAL POWER GENERATION (Common T.G.) 20 MW

Waste Heat Recovery Steam Generators (WHRSGs) for Sponge Iron Kilns

Each Kiln has a Waste Gas Volume of 22,000 to 25,000 Nm3 discharged at 850 to 9000C (9500C

maximum).The gas is presently being cooled in a Gas Cooler to a temperature of about 1800C

and then cleaned in an electrostatic precipitator and then discharged by an Induced Draught

Fan into atmosphere through a Steel Chimney. The heat of the gases is presently not utilized for

any useful purpose.

It is possible to utilize the heat of waste gases by installing a Waste Heat Recovery Steam

Generator (WHRSG) for each Kiln. The well tried out configuration for WHRSG is comprised of

an Evaporator, Super-heater in two (2) sections and an Economizer which will bring down the

temperature of gases from 850-9000C to 1800C and produce 9 to 10 TPH Steam at a pressure of

66 Ata and 4900C.

Technological Features of WHRSGs

The technological features of the WHRSG shall be as follows:

Type: Single Drum Water Tube with Radiant Chamber

Type of Water Circulation: Natural Circulation

The boiler pressure parts shall consist of water wall system of Fin Welded membrane

construction, Super-heater Stage-I, Super-heater Stage-II, Spray Type De-superheater between

the super-heater stages to control the steam superheat temperature to 490 ± 5°C, Economizer,

Steam Drum, Risers & Down comers., The economizer shall be a plain tubular counter flow and

drainable type construction. In the economizer, the feed water shall be heated to a

temperature close to the saturation temperature by the outgoing gases.

In the steam drum, the water shall be received from economizer outlet header. The steam

drum is sized to have adequate steam space and water space. The steam drum is equipped with

internals, which remove the water particles from the saturated steam, before it enters into the

super-heater.

The steam generated in the furnace water walls is taken to the steam drum through a series of

riser tubes. The water wall bottom headers receive the water from the drum through a series of

down-comers. The entire super-heater area is arranged in the convection and radiant zone. The

super-heater heats the saturated steam from steam drum by absorbing the heat from the flue

Page 15: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

gas to the required temperature. The de-super-heater sprays feed water into the steam to

maintain outlet steam temperature to the required level.

Common System for a Pair of Kilns

The following items of equipment are proposed to be common for each pair of Kilns to bring

economy in capital cost without affecting the working:

Deaerator-Cum-Storage Tank having 20’ capacity.

Boiler Feed Water (BFW) Pumps (1 working + 1 standby)

Blow-down Tanks

One H.P. Dosing System with 2 working + 1 standby pumps. One pump shall dose one

WHRB.

One L.P. Dosing System with 1 working + 1 standby pump for serving the common

Deaerator.

The boiler shall have Digital Distributed Controls for the complete operation of the boiler in

conjunction with T-G set operation. Considering the temperature in the area, water cooled

condenser is installed for exhaust condensing.

ATOMOSPHERIC BUBBLING FLUIDIZED BED COMBUSTION (AFBC) BOILER

The boiler is envisaged to use the following solid fuels:

a. Char generated as solid waste in the existing Kilns. It has a calorific value ranging from

1800 to 2200 Kcal/Kg i.e. an average calorific value of 2000 Kcal/Kg. The annual

generation of Char is 30,000 T.

b. Coal with an average calorific value of 3600 Kcal/Kg. Annual requirement is expected to

be about 45,000 T

Selection of Type of Boiler

Based on the experience of working of boilers for identical application in similar plants,

an Atmospheric Bubbling Fluidized Bed Combustion (AFBC) Boiler is considered to be

the ideal choice. It has the following advantages:

No need to grind the coal as required for Pulverized fuel firing. The boiler uses a fuel

size of -6 mm.

As a result of better heat transfer, the unit size and hence the capital costs are reduced.

It can respond rapidly to changes in load demand since thermal equilibrium between

the fuel particles in the bed is quickly established.

Low combustion temperature of 800 to 9000C inhibits formation of nitrogen oxides.

Due to low bed temperature, it can use coal of high ash content upto 50%. Even coals

with 70% ash can be efficiently burnt.

Page 16: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Dolomite / Lime are used in the bed material to take care of sulphur in the fuel from

pollution point of view. Hence high sulphur coals can be used. The Flue Gas

Desulphurization System is not required, thus reducing the capital cost.

Combustion temperature can be controlled accurately which helps in achieving better

life of tubes in boiler components.

Description of Proposed AFBC Boiler

The Boiler selected for Coal & Char firing is atmospheric bubbling type fluidized bed combustion

boilers of 150 TPH steaming capacity (to ensure total 20 MW Power even when two kilns are in

operation) with following design features :

1. Natural Circulation Design

2. Balance Draft Furnace

3. Single Drum Construction

4. Under Bed Fuel Feeding System

5. Fluidized Bed Combustion

6. Top Supported Design

7. Semi outdoor Installation

The Boiler is designed for firing coal and char as the main fuel. The Boiler is lighted up using

Diesel Oil. The complete furnace section is made of water cooled membrane wall construction

arranged as a gas & pressure tight envelope. Refractory is provided inside the furnace on the

water wall for a suitable height.

The steam drum is designed and provided simple and efficient drum internals, resulting in high

steam purity at all load condition of boiler output.

The fuel preparation and firing system consists one twin type bunker for both coal and char.

The fuel feeder is provided with VFD to control the fuel feed quantity. Primary air transports

the fuel pneumatically into the bed through the fuel air mixing nozzles. Fuel is feed into the

fluidized bed through under bed coal feed piping and bubble cap type fuel nozzle. The draft

system for the boilers includes 1 no. I.D. Fan, 1 no. F.D. Fan, 2 nos. P.A. Fans.

Bed ash coolers are provided for cooling the ash discharged from the level of fluidized bed

during operation. It consists of a small fluidized bed with air cooling. The complete boiler is top

support design and integral piping, valves and fittings, air and flue gas ducting, refractory /

insulation with necessary fixing components, aluminium claddings provided for boiler. Ducting

system is provided with necessary supporting steel work, expansion joints, dampers etc.

Primary and secondary air flow measuring devices are provided in the system. Necessary

secondary and isolating dampers are provided for efficient and safe operation of the boiler.

Secondary dampers are pneumatically operated and fan isolation dampers are motor operated.

Page 17: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Electrostatic precipitator is envisaged for dust collection. The ESP is designed to limit the outlet

emission to 50 mg/Nm3. The blow down system for the boiler includes one of CBD and one IBD

tank with all associated drains and vents, level gauges, temperature and pressure gauges etc.

The boiler is provided 2 nos. of feed pump along with motor drive. One spray-cum-tray

deaerator with storage tank is provided.

T.G. SET

One Steam Turbo Generator set suitable with Air/ water Cooled Condenser with an output of

20 MW is proposed to be installed. The salient features of the equipment are:

Turbine

Type : Horizontal single cylinder, single controlled extraction (common to Process and Deaerator heating) cum Condensing, multistage.

Inlet Steam Pressure : 66 Ata

Inlet Steam Temperature : 4900C

Generator

Rated Output : 20 MW

Speed : 1500-1800 RPM

Output Voltage : 11 KV

Power Factor : 0.8 – 0.85

TG Set will include Gear Box, Lubricating Oil system and all other accessories including control

system.

FUEL REQUIREMENT

Calculation of mixed fuel requirement:

WHRB

HOT FLUE GASES 4 x 25000 Nm3/hr from ABC of DRI kilns

AFBC

ITEM Composition per unit of fuel

Requirement MT per day

Requirement MT per year

b. CHAR (CV – 2000 Kcal/Kg) 0.40 150.00 45000.00

d. COAL (CV – 3600 Kcal/Kg) 0.60 220.00 67500.00

Page 18: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

3.4 PROCESS DESCRIPTION FOR SUBMERGED ARC FURNACE

TECHNOLOGY FOR FERRO ALLOYS

Selection of suitable production process and the capacity of the production units form

the nucleus around which the basic concept of a plant is developed. While the selection

of a process takes into account factors like type of product, availability of local raw

material, process status, specific energy consumption, level of energy required,

environment, and pollution etc., the capacity selection of major units would depend on

the volume of production, available unit sizes, economies of scale etc.

PROCESS DESCRIPTION

Ferro Alloy production was started in India with Ferro Manganese produced through

Blast Furnace route. However, Submerged Electric Arc Furnace route has been mainly

adopted for Ferro Alloy production since 1951. Though several types of Ferro Alloys are

in vogue, the major Ferro Alloys are Ferro Manganese, Silico Manganese, Ferro Silicon

and Ferro Chrome. Production of Ferro Alloys calls for availability of right type of ore

and quality power at the optimum parameters. India is fortunately endowed with good

reserve of ores such as Mn Ore, Coal and Quartz etc, which are suitable for Ferro Alloy

production. As such, it is a right place for ore based Ferro Alloys production.

Submerged Electric Arc Furnace route with 15 MVA modules has been selected as the

technology for this project.

This plant shall be designed for production of Manganese Alloys (Ferro Manganese &

Silico Manganese). However, provisions shall be kept for production of other ferro alloys

after carrying out some minor modifications. For exports, the standard grade of Ferro

Manganese has Mn content of ~75% and Silico Manganese has Mn content of ~65% and

Si content of 15-17%.

The production of Manganese alloys is a continuous slagging process. The oxide of

manganese, iron, silicon, phosphorous etc. contained in the ore is reduced by the

carbon present in coke/coal in a submerged electric arc furnace. The reduction of oxide

is accompanied by evolution of gases at furnace top.

Page 19: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Silico Manganese / Ferro Manganese / Ferro Silicon

Silico Manganese is an alloy of manganese with silicon & iron. In Ferro Manganese, Si is

present in much smaller quantities. Manganese alloys are widely used in metallurgy as a

complex reducer and alloying additive in making various grades of steel.

The concept of the use of Silico manganese instead of Ferro silicon pure into the steel is

due to its cost effectiveness, as Ferro silicon require purer raw materials, which are

costlier. Moreover silico manganese goes for production of refined grades of Ferro

manganese i.e. low and medium carbon Ferro manganese. Ferro manganese, on the

other hand is used where Si content in the finished steel has to be controlled accurately

as is the case in steel flat products (sheets and plates).

Silicides of Manganese are more stable compounds than manganese carbides.

Therefore, the higher the Si content in manganese alloys, lower is the carbon content.

Manganese alloys are produced by simultaneous reduction of silica and manganese

monoxide by the coke carbon contained in a mixture of manganese ore and manganese

bearing slag and quartz.

The chemical reactions taking place in the furnace are as follows:-

De-composition:

4 MnO2

=> 2 Mn2

O3

+ O2

( at 430o

C)

6 Mn2O

3 => 4Mn

3O

4 + O

2 (at 950

o

C)

Reduction:

Mn30

4 + C => 3MnO + CO

MnO + C => Mn + CO (at 1430o

C)

SiO2

+ C => Si + CO2

(at > 1500o

C)

The Mn and Si thus formed join the alloy.

The excess SiO2, AI

2O

3, oxides of calcium and Magnesium get generated during the

process and join the slag. In the process 0.7 – 0.9 Tonne of slag produced per tonne of

alloy. This would be sold for land filling purposes.

Fluxes may be added to the mixture to reduce Manganese losses to slag.

Alloy and slag are tapped simultaneously 3 - 5 times per shift.

Page 20: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Manganese - Iron

Iron and manganese are completely miscible in the liquid state. When the manganese

content is high, the liquids and the solids lines almost coincide. The solubility of

manganese in a-iron and in y-iron is limited. When manganese content reaches 10%, a

transformation of a-iron into y-iron is noticed.

When the manganese content is from 10-13% to 20-25% a c-phase in a hexagonal close-

packed lattice is formed. No transformations are noticed for alloys containing from 25-

40% manganese: a range of solid solutions of Y-Fe and Y-Mn exists down to room

temperature. Manganese does not combine chemically with iron.

Manganese - Carbon

Manganese combines with carbon to form stable compounds. The manganese carbides

Mn3C4 and Mn3C are known as the free energy of formation of Mn3C from the elements

is expressed for the high temperature range by the following equation.

∆Z0 = 3,870 + 3.63 T

Manganese – Iron – Carbon (Mn-Fe-C):

It follows that beside the two-phase ranges Y+Z and Y + carbide, a three-phase range y +

a + c also exists.

Different methods of carbon silicon manganese production may be employed in the

electric furnaces: the flux process and the self-fluxing one.

Smelting Process

When the charge is smelted, manganese monoxide forms silicates with the silicon

contained in the ore and the coke dust ash, which hampers the process of manganese

reduction. The flux process is based upon the fact that when lime is introduced into the

charge, MnO is displaced from the silicate by calcium oxide, and, as a result, losses of

manganese in the slag are reduced.

On the other hand, the smelting process in an electric furnace is accompanied by

evaporation of manganese, which increases with the rise of the temperature in the

furnace. In this connection, it should be noted that an increase of the basicity of slag

causes the temperature of the process to rise and the losses of manganese by

evaporation to increase. These two contradictory factors should be taken in account

when choosing the best possible slag schedule. The slag basicity to be selected depends

on the composition of the ore, and it ranges between 1.1 and 1.4. Under these

conditions, at a normal run of the furnaces, 80% of manganese contained in the ore

passes into the metal, 8-10% passes into the slag, and 10-12% escapes with the gases.

Page 21: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

When operating on basic slag, silicon is reduced only a little, and its usual content in the

metal does not exceed 2.0%. Phosphorus contained in the ore is mostly reduced and

passes into the alloy.

On the basis of the available thermodynamic data, only a qualitative description of the

processes of reduction of phosphorus can be given. The relation of the free energy of

reduction of P2O5 to the temperature says that, when phosphorus is reduced by carbon,

according to the reaction.

2/5 P2O5 + 2C = 4/5 P+2CO; ∆Z0 = 94,600 = 91.27 T

The process begins at 7630C.

It should be noted that the manganese formed also easily reduces phosphorus,

according to the reaction.

2/5 P2O5+2Mn = 4/5 P + 2 MnO; ∆Z0 = 42,800 - 10.12 T.

Reduction of phosphorus in the process of ferromanganese production will proceed

even more completely because of the formation of stable phosphides of manganese,

which displace the equilibrium in the direction of reduction of phosphorus.

The experience confirms that up to 90% of phosphorus contained in the ore can be

reduced. The reduced phosphorus partly evaporates and escapes from the furnace, and

80% of the total amount of phosphorus introduced with the charge passes into the

alloy.

As far as Sulphur is concerned, the high temperature and reducing atmosphere of the

ferromanganese smelting process, as well as the negligible solubility of manganese

sulfide (MnS) in the metal, promote its removal from the alloy. Therefore, its content in

ferromanganese does not, as a rule, exceed 0.05%.

The distribution of Sulphur between the metal and the slag is as follows: about 1% of

the total sulfur quantity introduced with the charge passes into the metal, 40-45%

passes into the slag and up to 55% escapes with the gases.

The manganese ore gangue, consisting mainly of silica, starts to smelt with manganous

monoxide already at 1,2500C, forming low-melting manganese silicates, which contain

38% SiO2 and 62% MnO. Later, silica and alumina contained in the ash of the reducing

agent as well as calcium oxide introduced with the lime are added to this smelt.

The content of SiO2 in the slag depends on the chemical composition of the raw material

and ranges between 25 and 30% while the manganese content is usually about 15%.

The melting point of such slag is between 1,300 and 1,4000C; the slag are mobile and

leave the furnace easily.

Page 22: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

The self-fluxing method of production of carbon silicon manganese is being used for a

long time world wide now. The essence of this method is that no lime is introduced into

the charge, and that the slag obtained by smelting, which contains 30-32 %Mn, about

30% SiO2 and about 0.03% P, is used for smelting manganese-silicon. By this method

60% of manganese passes from the ore into the alloy, 30-32% remains in the slag, and 8-

10% escapes.

In addition, when manganese-silicon is produced form slag, not less than 70% of

manganese contained in it is extracted.

Thus, the total extraction of manganese from the ore is 81-83% instead of 80%

extracted by the fluxing method. In addition, the absence of flux in the charge during

the production of carbon ferromanganese permits the productivity of the furnaces to be

increased considerably and the specific power consumption to be reduced from 3,600 to

2,800 KWH.

Ferromanganese is smelted in electric furnaces by a continuous process, slag and metal

being tapped at regular periods of 2 - 2 .50 hours. Slag is tapped from the furnace and

after solidification broken to size and sent to the silico manganese furnace.

The metal is tapped into CI Pans and after solidification broken to size and sent to

dispatch after analysis.

When carbon ferromanganese is smelted by the self-fluxing method, care should be

taken that the manganese content of the slag should not be too high, since slag

containing more than 40% Mn intensely attacks the lining of the electric furnaces. The

technical and economic characteristics of the production of carbon ferromanganese

depend largely upon a correct selection of the electric operation schedule of the

smelting.

Ferromanganese smelting should be conducted at a lower secondary voltage than that

of ferrosilicon.

The drop in the extraction of manganese and the rise of the specific consumption of

electric power when the voltage rises above a certain defined limit, which is lower for

the smelting of ferrosilicon, is chiefly determined by the following two peculiarities of

ferromanganese production:

First, manganese has a high vapour pressure, and for this reason losses of manganese

under normal conditions of production reach 8-10% while an incorrect electric

operation schedule may result losses up to 20%.

To reduce manganese losses by evaporation, it is necessary to prevent the formation of

superheated zones in the furnace. The electrodes should be place sufficiently deep in

Page 23: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

the charge to enable the manganese vapours to condense in the upper layers of the

charge.

Secondly the initial temperature of the reduction of manganous oxide to carbide, (1223 0C) and the initial temperature of formation of slag (12500C) practically coincide, which

may cause (under favourable conditions) the passage of a considerable part of MnO into

the slag. On the other hand, reduction of MnO from the silicate, present in the fluid slag

requires considerably more time and power than when it is reduced in the solid state.

Under these conditions slag will leave the furnace with an increased Mn content, and at

the same time coke dust not participating in the reaction, will accumulate in the

furnace, disturbing the operation of the furnace.

The components of the charge for making HC Ferro Manganese are Mn Ores, Reducers

like Nangal Coal, Hard Coke with fluxes like Dolomite.

Upon appropriate pre heating of the newly made furnace lining, the furnace is charged

with a charge for making necessary grade of Alloy, with the charge level and the

electrical load being raised gradually. Normal operating conditions are established in 3-

5 days from the beginning of charging. The process of making these two Alloys produces

slag which is tapped together with the metal through the same tap hole.

Raw materials for the above Products will be transported on daily basis from the yard to

the storage and weighing terminals, with the help of pay loaders/tippers. Then the raw

materials will be transported to the storage day bins by means of belt conveyors

through Screens.

They will be drawn from different storage bins into common weigh hoppers in a

predetermined proportion with the help of an Industrial Computer - PLC based

electronic weighing system which will be located in the furnaces’ control room. The

recipe will be set by the metallurgist from time to time based on the analysis of the raw

materials. The weigh hoppers will be supported on hermetically sealed electronic load

cells. The mix thus drawn into the weigh hoppers is commonly called burden or charge

and will be discharged onto a series of belts. The charge will be transported by the

designated conveyors and will be distributed into various charging hoppers located

around the furnace on the top floor of the furnace building. The charging hoppers are

connected to the furnace by chutes with intermediate gates which will be pneumatically

actuated. Whenever the furnace operator actuates the gates to open, charge is

unloaded into the furnace.

Page 24: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

TAPPING & TEEMING INTO CI MOULDS FOR THESE PRODUCTS:

Tapping is done periodically about 10 -12 times a day as per a specified schedule and

based on the power consumption.

The tap hole is opened with Oxygen Lancing and/ or MS round via an arcing gun. The

melt runs out through the hole and begins to pass on to the launder to CI Pans. The

tapping time is around 10 minutes. The Alloy and Slag are separated through natural

Density difference via a Skimmer Block arrangement and are routed to two different

series of CI Pans which are appropriately cascaded.

Samples of Alloys / Slag are taken for analysis during tapping.

The liquid Alloy viz., HC FeMn /HC SiMn is cast in moulds in thin cakes which are broken

to required sizes after solidification, weighed and packed.

The Slag of HC FeMn is broken to size after solidification and is used as input for

production of HC SiMn and the Slag of HC SiMn is broken after solidification and

dumped into the Slag Pit.

The tap hole is opened with Oxygen Lancing and / or MS round via an arcing gun. The

melt runs out through the hole and begins to pass on to the Ladles. The tapping time is

around 10 minutes. A sample of any Alloy metal is taken for analysis during tapping.

The liquid Alloy is cast in moulds in thin cakes through decanting of the ladle which are

broken to required sizes after solidification, weighed and packed. The product mix for

this unit will be limited to Silico Manganese and Ferro Manganese; No Ferro Chrome will

be manufactured without prior approval of the ministry.

BRIEF PROCESS OF MANUFACTURING

INPUT OF SIZED & GRADED RAW

MATERIAL

HANDLING BY PAYLOADER & DUMPERS

FEED IN DAY BINS THROUGH BELT

CONVEYOR

BATCH PREPARATION BYCOMPUTARISED

WEIGHMENT

TAPPING IN CAST IRON LADLES

DISCHARGE OF MOLTEN METAL

REACTION IN FURNACE CHARGE INTO FURNACE

DISCHARGE OF SLAG SALE FOR LAND FILLING

NATURAL COOLING SIZING, GRADING &

PACKING INSPECTION DESPATCH

Page 25: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Raw Material feeding system

Raw Material shall be fed to a ground hopper by dumpers. The material shall be drawn

from ground hopper to screening station where fines shall be removed. The screened

material shall be conveyed to the Bunker house having day bunkers for different

materials. The bunkers shall be fed with reversible conveyors.

Each bunker shall be provided with vibratory feeder and set of weigh hopper. Material

from each bunker shall be withdrawn and weighed separately in the weigh hoppers and

dumped to a common surge hopper provided with a vibratory feeder through a

conveyor.

The weight of raw materials in required quantity from the surge hopper shall be fed to

the feed hopper provided at the top platform. The material from feed hopper shall be

conveyed to charging bins and correction bin, which will be located around the

circumference of the furnace. These charging bins shall feed the raw material mix

through chutes and slide gates into the furnace.

Electrical

Furnace transformer rating - 1 nos. 15 MVA single phase per furnace

The furnace shell shall be lined with graphite paste inside. Layers of high heat duty

firebricks and insulation bricks will back this. Tapping holes (3 nos at 1200) will be

provided at the hearth level in the refractories. The bottom lining will be thick layer of

tamping paste and layers of high alumina brick of 55%, 45% and 35% Al203 and suitable

castable refractories. Silicon carbide bricks will be used for tap hole lining.

The furnace shall be provided with water-cooling system for:

Cooling of current conducting pipes and contact clamp.

Cooling of electrode holder ring

Cooling of electrode shell

Cooling of supporting framework exposed to heat from furnace top.

For furnace tapping, tap hole arcing device (moving around the furnace) shall be

provided. Electrical connection to the arcing device shall be made manually after

positioning.

The flue gases from the furnace are sucked through an inter-connecting ductwork and

gas cleaning system by induced draft fan and exhaust to chimney. The gas is first cooled

from 300 0C to 120 0C in a heat exchanger. The cooled gases pass through a bag fitter for

dust removal before letting it out through chimney.

The tapping fumes are also cleaned through bag filters before letting it out.

Page 26: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Hot Alloy handling

The hot metal tapped from the spout will be collected in a ladle on rails. The slag will be

collected in C.I. Pots mounted on rails.

The liquid metal from the ladle will be poured to CI mould with the help of a crane. The

thin casting, which is cast in mould, will be transferred to a crushing and packing area by

dumpers. Thereafter, manual breaking and packing shall be carried out for dispatch.

Primary Parameters of Ferro Alloy Furnaces

SL No Parameters Unit Value / Features

1 Ferro Alloy production t/yr Silico Manganese 24750 TPA or Ferro Manganese 35640 TPA or Ferro Silicon 13860 or Product mix

2 Daily Production TPD Silico Manganese 75 TPD or Ferro Manganese 108 TPDor Ferro Silicon 42 TPD or Product mix

3 Number of Furnaces No 1 (15 MVA)

4 Type of Furnace Submerged Arc Furnace

5 Transformer Rating MVA 1 x 15 MVA single phase per furnace

6 No of Electrodes No 3 in each furnace

7 Type of electrode Self baking Soderberg

QUANTITY OF INCOMING MATERIALS & SOURCE

SILICO MANGANESE – 75 TPD (24750 TPA)

SL Material Specific

Requirement Total requirement

MT /Day Total requirement

MT /Annum

1 Mn ore/ FeMn Slag 2.2 165 54450

2 Coke 0.5 37.50 12375

3 Quartz 0.6 45 14850

4 Dolomite 0.25 18.75 6187

5 Elect. power 4100 Kwh 307500 Kwh 101.475 mio. units

6 EC paste 0.035 2.62 866

Page 27: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

FERRO MANGANESE -108 TPD (35640 TPA)

SL Material Specific

Requirement Total requirement

MT /Day Total requirement

MT /Annum

1. Mn ore 1.8 194.40 64152

2. Coke 0.6 64.80 21834

3. Dolomite 0.3 32.40 10692

4. Elect. power 2700 Kwh 291600 Kwh 96.228 mio. units

5. EC paste 0.025 2.7 891

FERRO SILICON – 42 TPD (13860 TPA)

SL Materials Specific

Requirement Requirement

MT/day

Requirement

MT/year

1 Quartz 1.800 MT 75.6 24948

2 Coke 1.095 MT 45.99 15177

3 Mill Scale /

iron ore 0.400MT 16.8 5544

4 Electric power 7700kwh 323400 106.722 mio. units

5 EC Paste 0.050 MT 2.1 693

It is committed that no charcoal or char will be used, instead of char from local source; coke will be used as fuel.

The quality of raw materials is key factors for effective plant operation.

The raw materials, required for manganese alloys production are:

For Silico Manganese / Ferro Manganese

Manganese Ore

Ferro Manganese Slag

Coke

Dolomite

Quartz

The sources for the above have to be critically selected to get the required product. Manganese Ore:

Mn - 35-40%

Page 28: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

P - 0.10% (typical) Size - 10-80 mm

The ore would be procured form Joda-Barbil area of Orissa & from MOIL in the Nagpur sector.

Ferro Manganese Slag:

MnO - 30-35%

P - ~0.02%

Size - 20-80 mm

The above material would be generated during the in-house production of ferro manganese. This would be crushed to size and used as an input to silico-manganese. If sufficient quantities are not available in-house, it could be procured from indigenous sources or even imported.

LAM Coke:

Ash - 14-18%

Size - 5-25 mm

Metallurgical coke shall be purchased from the open market from producers based in

Dhanbad belt of Jharkhand.

ENERGY BALANCE & POWER REQUIREMENT

Specific energy consumption per unit of product will be as below:

FeSi - 7700 KWh

SiMn - 4200 KWh

FeMn - 2700 KWh

Based on the above specific consumptions the total power requirement for the plant is estimated as 20 MW which will be available from JSEB

4 D G set of 100 KVA will be installed for Emergency power supplying to various critical areas like cooling water pump, crane and lighting to take care of on process work during main power soupy failure.

Diesel consumption when D.G in operation will be 25-30 liters per hour

TYPES AND MAJOR SOURCES OF POLLUTION

Proposed production

facilities Process operation

Pollutants released

Type of environmental

pollution

Raw Material Handling

Unloading, Stocking Dust Air Pollution

Page 29: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Raw Material Feeding

Feeding RM in stock Bin & SAF Dust Air Pollution

Production Process Melting of Raw material, Chemical Reaction in SAF

Fume & Dust Air Pollution

Product Processing Molten Metal Discharge and Slag Discharge

Solid Waste in form of Slag

Land & Soil Pollution

Product handling Sizing, Storage, Loading & Transporting of Product

Dust Air Pollution

Mitigative Measures for environment management

With increasing environmental awareness, it is imperative that due attention is paid to this aspect right at the planning stage. Of the three major identified areas of pollution viz. air, water & noise, the extent of water pollution & noise pollution in ferro alloy manufacturing units is negligible.

As regards air pollution, while gaseous emission are naturally well within the stipulated limits, necessary control measures will be put in place to ensure that particulate emission from the furnaces are also well below the acceptable / prescribed safety norms.

a) Ambient Air Quality Management:

Fume extraction system for suction of fugitive emissions from raw material

charging area and then to bag filter

Water sprinkling and green belt development for maintenance of other areas

Bag filter system for control of emissions and dust from charging of sub merged

arc furnace through fume extraction system

Fugitive emissions can also be kept low by making pucca haul roads within the

premises and making arrangements for water spraying at all the dusty places in

the premises and during loading, unloading process.

Control of Stack Emissions and Fugitive Emissions will have a direct impact on

the ambient conditions.

Development of planned green belt in the industry will also control ambient

conditions

Page 30: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

b) Solid Waste

Quantity of solid waste generation is about 43.6 TPD at final stage after

commissioning of the fourth phase. Appropriate disposal program must be

undertaken. The solid waste is not hazardous in nature. It shall be used for land

filling.

SL No PRODUCT Solid waste generation

per MT of Product Handling / Disposal

1 Ferro – Silicon Nil under normal

operation -

2 Silico – Manganese 0.45 MT Will be granulated and

used for landfilling

3 Ferro – Manganese 0.45 MT Will be used as raw material for silico –

manganese production

No petrography, chemical analysis or leachate studies for fly ash, muck, sludge and slag generated, has been undertaken as none of the raw materials used has any trace elements. However TCLP data was collected from secondary source for SMS slag as it will be handled in open. Management plan for the same is proposed as below:

TCLP data of slag (all in ppm) source – steel technology, internet

Parameter Cr 6+ F Cr Mn As Cd Hg Pb

Slag <0.02 1.85 <0.02 0.04 <0.02 <0.01 <0.01 <0.05

Management plan

Slag generated from the unit will be tested for actual concentration.

Methodical TCLP for at least 3 samples of actual slag will be taken up for ascertaining

its characteristic. If found to be hazardous will be handled as per norms – kept on

impervious/lined flooring and contact with liquid/water will be avoided.

Slag will be disposed to metal recovery unit for further processing

Maximum storage of slag only for 15 days within the unit.

Slag will be stored in a covered area.

Column leachate study for all types of stockpiles or waste disposal sites, at 20 0C –

50 0C should be conducted and reported after actual generation of the same

Page 31: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

3.5 Utilities Requirement – All Units

Water

Water requirement for power has been envisaged for “Water Cooled Condensers”. For the

existing unit and units in expansion total “Make-up” water requirement is as below:

Unit Final Installed

Capacity Existing

m3/day

Expansion

m3/day

Make-up water

m3/day

DRI Plant 400 TPD 300 - 300

SAF (Ferro Alloys) 15 MVA - 50 50

Power Plant 20 MW - 500 500

Drinking & Sanitation

5 5 10

Plantation &Env.

5 5 10

Total 310 560 870

Water requirement is presently sourced from ground water. For the expansion and at final

stage water will be sourced from DVC through surface pipeline to be laid after due permission

of the department.

Water Treatment Plant

The plant requires treated water in the water circuits meant to cool the equipment.

Raw water will be made to pass through the “Dual Media Filter” to arrest the suspended

particles, turbidity and iron present in water. Filtration systems remove particulate matter and,

because of the large surface area of filter media, they also can be used to drive chemical

reactions that result in the removal of several contaminants.

Plant Water System

Water will be required in Cooling Tower as make up. Water will also be required to produce

treated water to maintain its ppm or conductivity increased due to contamination in cooling

line. Raw water requirement for Cooling Tower, DM plant, area cleaning system etc will be will

met from Borewells. Water tank of adequate capacity (depending upon equipment

requirement & workforce) will be constructed within the premises.

Cranes

2 No. 35/10MT, 1No. 10MT and 1No. 15 MT Double girders, EOT Cranes will be required to

handle the raw material and finished product. All cranes will comply IS 4137 which is meant for

EOT Cranes in Steel Plants.

Page 32: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Compressed Air System

Compressed air is required primarily at three locations in the plant viz. in Induction Furnace, in

CCM & in Dust Extraction System (bag filter).CCM & Induction Furnace require 60 to 100 cfm

(FAD) air compressed up to 10-12 kg/cm2. Bag filter requires 2.1 Nm3/min (FAD) of air

compressed to a pressure of 6 to 7 kg/cm2. Two (2) air compressors will be installed along with

the drier to cater the above demands.

Fire Protection System

Adequate number of portable fire extinguishers will be provided at various locations in the

plant shed, LT panel room & DG Set Room.

Plant Electrical System

Plant electrical system will have a 33 kV outdoor type substation. It will have one incomer with

CT, PT, surge arrestor, isolators etc. It will have five outgoing feeders (two for furnace

transformers of approx. 7200 kVA (33kV/ 1000-1000V)). The power supply through furnace

transformers will be supplied to furnace whereas power supply through aux. transformer which

will be used for EOT crane operations, CCM operations, furnace auxiliaries, pumps for cooling

water lighting etc.

Cables, Cable Trays & Cable Trenches

Cables for Breaker operated feeders shall be chosen based on:

Load current with de-rating factor for ambient temperature, mode of laying, grouping

factor etc.

Short time current ratings with 0.2 seconds withstand time.

Cable for Switch-fuse controlled feeders shall be chosen based on:

Load current with de-rating factor for ambient temperature, mode of laying, grouping

factor etc.

Emergency power

1 X 500 KVA silent type DG sets have envisaged to power to the auxiliaries of Plant when JSEB

power is not available. This will also be useful for Emergency power to take care of safe shut

down of important auxiliaries of Plant. During total power failure, above DG set will also

support for Emergency lighting for personnel movement in important steel plant locations.

It has been proposed to install 3x500 KVA additional Silent type DG Sets.

Auxiliary Transformers

One (1) number 1750 kVA, 33KV / 433V transformers will be provided for all the plant auxiliary

loads. These transformers will be two winding, three phase type with ONAN Cooling. Off Circuit

tap changer has been envisaged.

Page 33: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Control & Relaying

The Steel plant Electrical power control is done at two different locations. One control & Relay

panel is installed in 33 kV substation for feeders whereas LT control is done by LT control panels

installed in LT panel Room or near the equipment (if required). All required control, protective

relays and metering for electrical installations to against abnormal system conditions will be

provided in these control rooms.

Protective System

For protection of equipment against abnormal system conditions, adequate protective devices

will be installed in the respective switchgears and/or control and relay panels. A group of such

protective devices will be necessary to protect the equipment under different abnormal

conditions arising in the system.

The following protection will be provided for major electrical equipment:

(a) For Furnace Transformer

1. Over Current Relay

2. Earth Fault Relay

(b) For Auxiliary transformers:

1. Inverse time over-current relay with high set instantaneous unit for phase faults.

2. Definite time over current relay for earth fault

3. Back-up earth fault on LV-neutral

The protections provided for different kind of feeders in 33 kV switchgears are as follows:

(a) Incomer/Tie/Feeder

1. Inverse time over current relay for phase fault

2. Definitetime over current relay for earth fault

(b) Motors

1. Comprehensive motor protection relay

2. Differential protection for motors rated above 1 MW (if any)

In all cases, proper discrimination would be achieved so as to isolate the faulty elements only,

keeping the healthy part of the system in service.

Page 34: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Power

Power sourced initially from DVC for construction/erection and preliminary work. Presently

0.85 MW load sanctioned. Later on power will be sourced through the CPP as it will be

commissioned simultaneously with the other units. After the installation of expansion units the

power generation of 20 MW will be used as below:

Unit Existing (MW) Proposed (MW) Total (MW)

DRI Sponge 1.350 1.350

SAF - 15 MW 15 MW

CPP Auxiliary - 1.65 1.65

TOTAL 1.35 16.65 18.00

Manpower

A total of 250 personnel comprising Technical Managerial & Supervisory Staff and Directly

Employed Manpower is proposed to be newly employed as follows:

Existing Sponge Iron Plant : 250 personnel

Power Plant : 50 Personnel

Submerged Arc Furnace : 100 Personnel

Total : 400

Indirect employment generation is expected to be more than 600 persons.

Facilities for the Employees

The following facilities will be provided in the power plant;

Administration building and technical office

Construction offices and stores

Time and security offices

First aid and rest rooms

Canteen and welfare centre

Toilets and change rooms

Car parks and cycle/scooter stands.

Page 35: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

3.6 Pollution Control Devices/System

The following measures for minimizing adverse impact on the environment have been

incorporated for DRI and proposed for SMS plant and CPP.

UNIT AIR POLLUTION CONTROL SYSTEM

1 Sponge Iron Plant ESP used to control dust emission through flue gases from DRI kilns after WHRB. All conveyors covered. Stack Height will be raised to meet the emission norms.

Bag filters used installed at Stock House, Crusher House, Coal injection point, Intermediate bin, Cooler discharge section and product House to control fugitive dust pollution

Solid waste (dolochar, coal fines) will be used as fuel in captive power (AFBC) plant

2 Captive Power Plant

ESP will be provided to control dust emission through flue gases from AFBC. Stack Height will be raised to meet the emission norms.

Fly ash generated will be supplied to cement industries or disposed as per prevailing norms.

Dry collection of fly ash and storage in silos. Transportation of fly ash in closed containers.

3 SAF (Ferro Alloys) Bag Filter System of suitable capacity will be provided

4 Raw Material & Product Handling

(Fugitive Emissions)

Bag filters will be used at Coal handling section, Iron ore handling section, Stock house & Product house section to control fugitive dust pollution

Water sprinkling will be done during unloading/loading of trucks to control fugitive emissions

Raw materials & Products will be kept in covered sheds or bunkers & all conveyors will be covered.

5 Overall Plant Area Pucca roads within the premises, water sprinkling in dusty areas and green belt/green cover in 33% of total area to arrest the fugitive dust emission

Fugitive emissions will also be kept low by making pucca haul roads within the premises

and making arrangements for water spraying at all the dusty places in the premises and during loading, unloading process.

Control of Stack Emissions and Fugitive Emissions will have a direct impact on the ambient conditions.

Development of planned green belt in the industry will also control ambient conditions.

Page 36: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

The fugitive emissions of particulate matter will be maintained below 2000 µg/m3 at a distance of 10 m from the sources.

The onsite & off-site emergency plan will be an integral part of any major hazard control system. It will be based on those hazards/risks identified by the works management, which could affect people and the environment outside the works.

Water will be in closed circuit system. Hence no industrial effluent will be generated.

Domestic waste water will be partly used for horticulture and partly disposed through septic tank pit combination.

Solid waste generated will be reused as follows:

Dust from bag filters will be partly re-used in process or construction material and filling

Dolochar & coal fines used as fuel in AFBC. Fly ash generated from the process sent to cement plants.

Slag from induction furnace will sold to metal recovery units and will be used for road making etc.

Implementation of Rain Water Harvesting for use of harvested water in the plant.

Peripheral development activities will be undertaken as detailed in later chapters.

Stack height for all de-dusting units will be 30 m as per CPCB regulation.

Waste heat utilization for power generation will be followed.

Adequately designed ESP will be installed to achieve the prescribed stack emission standards of 50 mg/Nm3.

Pollution Control and Monitoring areas

SL No Area Monitoring Location

1 Raw material handling area Wagon tippler, Screen area, Transfer Points, Stock

Bin area Fugitive Emission

2 Crusher area Crushing plant, vibrating screen, transfer points

3 Raw material feed area Feeder area, Mixing area, transfer points

4 Cooler discharge area Over size discharge area, Transfer Points

5 Product processing area Intermediate stock bin area. Screening plant,

Magnetic Separation unit, Transfer Points, Over size

discharge area, Product separation area, etc. 6 Other areas Areas as specified by State Pollution Control Board

Page 37: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Waste Water Treatment

Water Pollution mainly comprises of inorganic solids, oil, grease etc. in suspension, solution,

and emulsion. Two aspects to be considered for water treatment are:

In view of the technological constraints, there will be blow downs from each of the

systems to ensure safe operations of the plant. It is suggested that the blow downs water

be collected centrally and treated to make the water usable in less critical applications like

slag quenching, green belt development etc. Neutralization of acidic water, Settling and

clarification followed by filtration will be implemented for making the waste water

reusable.

All efforts will be made to re-use and re-circulate the water and to maintain zero effluent

discharge.

Page 38: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER –4

SITE ANALYSIS

4.1 LOCATION

The site is located at Manjhiladih, P.O. – Gadi Srirampur, Dist- Giridih, in the state of Jharkhand

and is about 0.8 km from Dhanbad Giridih State Highway and 6.00 Km from Giridih Railway

Station.

Impact due to project location is envisaged in absence of proper pollution abatement measures

and environment monitoring plan, as it is situated at a close distance from various

environmental sensitive locations like human habitation, railway line, water course, etc.

Adjacent habitation at village Manjhiladih is in the vicinity of 0.5 km, densely populated area-

Giridih at 6.0 Km, River Usri at 1.75 Km and Barakar Nadi at 7.0 KM. The land is fallow – open

and already developed for industrial use.

The site is located close to the raw material area and even closer to users of product. Electricity

for the plant will be sourced through its Captive Power Plant and DVC. Transportation facilities

to access various markets are readily available. Both skilled and unskilled labour is available in

the area. Also the location of the plant is suitable as it meets distance criteria from the various

landmarks for environment related requirements.

Fig: Google Image of Project Site

Page 39: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Fig: Key Plan

Page 40: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Fig: Layout Plan

Page 41: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Environmental consideration while selecting the site:

• Existing site with facilities and no additional land requirement

• Proximity to Raw Material sources

• Easy accessibility of rail & road infrastructure

• Existing topography of land with slope & drainage in the area

• Availability of land avoiding:

Forest Land

Prime Agriculture Land

Displacement & Rehabilitation or Scarce resources

Plant layout developed considering the placement of technological and services units so there is

no interference and the movement of man/material is easy and minimum.

SITE DESCRIPTION

No. Features Details

1 Village, District and State Village: Manjhiladih, P.O: Gadi Srirampur,

District - Giridih, State Jharkhand

2 Survey of India Topo. sheet covering the

plant and surroundings 73 L/8 (G45U8)

3 Latitude 24° 07’ 01.62” N

4 Longitude 86° 21’ 10.60” E

5 Land use at the proposed project site Use in industrial activity

6 Nearest Highway/State High Way Dhanbad Giridih SH at 0.8 KM

7 Nearest Railway Station Giridih

8 Nearest major habitation Giridih

9 Nearest River Usri Nadi

10 Forest Forest, Hills, in buffer zone only

11 Ecologically sensitive zone Nil within 10 Km radius

12 Nearest Port Haldia Port in West Bengal

13 Defense Installation Nil within 10 Km radius

14 Historical Places Nil within 10 Km radius

15 Dams and Barrages Nil within 10 Km radius

Page 42: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Land

The general layout of the proposed plant has been developed keeping in the view the following

factors:

Uninterrupted flow of materials in accordance with the technological requirements.

Contours and gradient of the site

Optimum lead for transport of materials and for service lines

Predominant wind direction

Logistic approach in location of technological units as well as service facilities

Safety clearances & statutory provisions

Close proximity to rich raw material sources

Land use Break-Up

SL TYPE OF USE Area (ha.) Area (acres)

1 Plant area after expansion 6.00 14.80

2 Administrative offices and other buildings. 0.46 1.15

3 Roads and Paved Area 0.81 2.00

4 Storage and solid waste handling area 0.20 0.50

5 Green Belt & open area 3.72 9.20

TOTAL LAND ACQUIRED 11.10 27.65

LOCATION ADVANTAGE - Advantage Jharkhand

Page 43: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Jharkhand shares its border with the states of Bihar to the north, Uttar Pradesh and

Chhattisgarh to the west, Orissa to the south, and West Bengal to the east. The commercial city

of Ranchi is its capital. The other major cities and industrial centers are Jamshedpur, Bokaro,

Giridih and Dhanbad.

Page 44: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER -5

PLANING BRIEF

M/s Atibir Industries Co. Ltd. is promoting Sponge Iron Plant for which the configuration of the

unit is as follows:

Existing:

4 x 100 TPD Sponge Iron Plant

Proposed:

20 MW Power Plant using WHRB and AFBC boiler.

15 MVA submerged Arc Furnace for Ferro Alloys.

The promoters have a long experience in mineral and metal trade and implementation of the

project in time will not be a problem.

Schedule of implementation of the project is the most reasonable time during which the

proposed project can be implemented. This takes into account the time required for various

activates i.e. acquisition of land, detailed engineering of the unit including architectural and

structural designs, civil construction Procurement of equipment and machinery including

utilities and services, equipment test and trial runs etc.

Key factors that would facilitate successful and timely project implementation are:

o Proper choice of technology and machinery suppliers.

o Adequate diligence in formulating the technical concept and system design / selection of

the plant.

o Proper choice of contractors for civil construction and erection of equipment.

o Formulation of effective project team led by an experienced Project Manager.

o Establishment of an efficient system for project planning & monitoring including reporting

procedures for progress review & co-ordination.

o Customization of project execution plan to suit the promoter’s profile.

Implementation Strategy:

Typically any project has four core dimensions viz:

o Engineering: this directly impacts the smooth operations of the plant over its life.

o Procurement: is critical on account of the impact that it has on investment and performance

benchmarks and also in ensuring the choice of appropriate technology.

o Construction: is critical in terms of its impact on completion quality and the duration of the

project phase.

o Project Management: other than its obvious impact on project timeliness it also contributes

to risk minimization for the promoter.

“Zero date” for a project is generally reckoned as the date on which the contract for “main

machinery” becomes effective.

Page 45: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

The plant & machinery for a project can be procured in three modes:

o Turnkey/ Semi-turnkey

o Package

o Shopping

For the project the turnkey mode of procurement for project execution is proposed. The

proposed solution shall help the company in optimizing project investment and minimizing

entrepreneur risk due to cost escalation. In the proposed solution, two agencies one for off

shore activities and the other for on shore activities have been considered.

Based on the consideration that pre-project activities are accomplished prior to the award of

the main machinery order, an implementation period of 24 months from the date of signing /

effectiveness of the contract has been envisaged.

Page 46: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER-6

PROPOSED INFRASTRUCTURE

Processing Area

The processing area will comprise of various plant facilities within the premises they are – Raw

material handling plant, DRI Kiln, SAF, TG House, Condenser, Cooling Tower, Roads &

infrastructure and water reservoir. Thus total area of 6.00 ha will be developed as processing

area.

Non - processing area

There is no proposal of any residential colony as the required manpower will be sourced from

local populace. Few highly skilled posts may be filled from outsiders for whom houses will be

leased in nearby residential area. Non-processing area will comprise of facilities within the

premises such as – Store & administrative block, road & yards and vacant area 1.47 ha

Green belt area

Green belt and plantation will be developed over the vacant plant area. Indigenous trees will be

planted in three tier system. Plantation will be started along with the construction. Total area of

3.72 ha will be developed as green belt and plantation.

Occupational Hazards

No major occupational health hazards are envisaged in plant after proper safety and

environmental protection measures. However the general hazards of iron & steel industry will

be there. The personnel will be trained to take sufficient precautionary measures for safety and

hygiene. Project activities are not likely to cause changes in occurrence of disease or affect

disease vector. Though, medical checkup of workers will be regularly done as per statute.

Hot Metal handling

The hot metal tapped from the spout will be collected in a ladle. The slag will be collected in C.I.

Pots mounted on rails. The liquid metal from the ladle will be poured to CCM section with the

help of a crane.

Resource optimization

Graded raw material with minimum impurities will be used for manufacture of DRI, SAF and

CPP. Handling of material will be done in an environment friendly manner. Process water will

be kept in closed circuit and will be recycled. Any waste water generated will be reused for

horticulture or dust suppression within the premises.

Page 47: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Solid Waste Generation and Handling

Item Description Qty. TPY Facility for control

Existing Sponge Iron Plant

Fine Iron Ore and Coal Dust

Screens, Stock House, Coal Injection

4,500 Bag Filter dust sold to Sinter Plants of other units

Ash After Burning Chamber-ESP

1,680 ESP dust sold to Cement block/Brick making

Char, Char Fines &Dolo-char

DRI Process 30,000 Presently sold to Power Plants.

To be used in-house in AFBC

Power Plant

Ash ESP of AFBC Boiler 40,000 The ash shall be collected in ash silo and disposed-off suitably to Cement Plants and Fly ash Bricks making units.

Coal Fines Coal preparation unit 7,500 Mixed with dolochar used in-house in AFBC

Ferro Alloys Plant

Bag Filter Dust Bag Filter 3,300 Bag filter dust to be sold to Sinter Plant

Slag Ferro Silicon Unit Nil under normal

operation NIL

Silico – Manganese

0.45 MT/ MT product

Will be granulated and used for land

filling

Ferro – Manganese

0.45 MT/ MT product

Will be used as raw material for Silico Manganese production

Hazardous waste: There is no hazardous waste from the plant except for used oil ~ 240 litres

per annum from various sections. This is saleable to the registered recyclers in the market.

Page 48: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER- 7

REHABILITATION & RESETTLEMENT (R&R) PLAN

R&R Plan – not required

No new/additional land is to be acquired. The existing land was purchased from the villagers on

mutual consent. Full amount has been paid and land acquired and bounded. There is no

displacement of any houses, habitation or livestock. Also the land acquisition has not rendered

any rayat land less or any worker on the land jobless, thus the project is not covered under R&R

plan.

However preference in employment given to land sellers and locals. Total 11.19 ha of land in

possession and industrial use.

Page 49: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER- 8

PROJECT SCHEDULE & COST ESTIMATE

M/s Atibir Industries Co. Ltd. has initiated to get clearances from the statutory bodies. The site

selected and land for the project is in industrial use and no additional land required to establish

the project.

The Consents required under Air, Water Acts will be obtained from JSPCB giving details of

Processes involved.

As land is Industrial land and not belongs to Forest, no clearance under Forest Act is required.

Project Implementation Schedule

The project schedule includes various activities like civil works, engineering, procurement,

erection and commissioning. It will be imperative to complete many activities before the zero

date and soon afterwards. These include:

Basic engineering

Clearance from statutory authorities

Land acquisition

Preparation & issue of tender document for major technological units

Placement of orders for major technological units

Financial tie-ups, if any and

Finalization of terms with overseas agencies if any.

The schedule for implementing the proposed project is as under

Particulars Start Completion for

SMS, CCM & CPP

Civil Works Zero date 04 months

Placement of Orders 1 months 06 months

Fabrication 2 months 14-16 months

Erection & Installation 8 months 20-22 months

Trial Production 23 months

Commercial Production 24 months

Page 50: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

Cost of Project: Total Project

SL No Details Rs. In Crores

EXISTING

Rs. In Crores

PROPOSED

1 Land & Site development incl. Boundary 0.83 3.00

2 Office Building, Shed Civil etc. 4.29 15.00

3 Plant & Machinery (incl. Pollution Control) 30.44 80.00

4 Contingencies - 7.00

Total 34.87 105.00

The company proposes for expansion to set up a SAF with CCM with capacity 240 TPD through

the existing Sponge Iron with Captive Power Plant, After reviewing the various probable options

including economical viability, power balancing, implementation schedule, it was concluded

that the above set up would be best suited for the project.

Page 51: PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTTenvironmentclearance.nic.in/writereaddata/Online/TOR/13... · 2018. 8. 13. · PPRROOJJEECCTT FFEEAASSIIBBIILLIITTYY RREEPPOORRTT

CHAPTER 9

ANALYSIS OF PROPOSAL

M/s Atibir Industries Co. Ltd. has initiated to get clearances from the statutory bodies. The

expansion will be within the existing premises l land for green cover, utilities etc. Details are as

below:

PROMOTERS : M/s Atibir Industries Co. Ltd.

Project : Iron & Steel

Plant location : Village: Manjhiladih, P.O- Gadi Srirampur,

District –Giridih, State Jharkhand

Markets : Jharkhand, Orissa & West Bengal – well connected

Plant capacity :

Sponge Iron – 120000 TPA, SAF (Ferro Alloys) SiMn 24750 TPA;

FeMn 35640 TPA; FeSi 13860 TPA or Product Mix

Captive Power Plant (WHRB+AFBC) - 20 MW

Raw material sources : Iron ore Mines in Odisha & Jharkhand

& Coal from CCL (Linkage & e-auction) – raw material available

Fuel : Indian coal – raw material easily available through Linkage & e-

auction

Water requirement : For process, domestic & others – 870 m3/day

Water sources : Being applied for Water Permission from WRD, GoJ

Basis for assessment : Per tonne of finished products

Max. power demand : 20 MW

Main units : DRI Unit, , CPP and SAF units

Main storages : For raw materials and products – space available

Estimated manpower : 400 Nos.

Implementation period : 24 months

Total Investment cost : Expansion Rs. 105 crores (Total - Rs. 140 crores)

Conclusion

Based on the performance indicators, the project is technically & financially viable, Under both normal and contingent conditions.