Santé Alexandra

Page 2: Santé Alexandra Overview 02

Santé Location

Page 3: Santé Alexandra Overview 02

Plant Entrance

Page 4: Santé Alexandra Overview 02

Plant Lay Out

Page 5: Santé Alexandra Overview 02

Santé Overview A – Opportunities and Strength

1 – Santé Alexandra is a Food industrial company for producing milk products , Juices and most types of cheese

2 – The company was established in Borg El-Arab City in Egypt as a closed joint- stoke under the investment law and since 2000

3 – The location of the plant in an area of Burg Al Arab industrial is far from Alexandria and airport Burg Al Arab by 30 kilometers and just 50 kilometers

from Nozha Airport and the port of Alexandria and factory overlooking the 4 – The Islamic Development Bank in Jeddah is the owner by 100 % since 2010

streets from all sides including the main road of Burg Al Arab 5 – The factory is located on an area of 42,000 m2 and buildings on an area

of approx. 20 000 m2 with availability to build on another 8 000 m2 as warehouses or Juice Concentrate Plant

6 – Processing equipment manufacturing by APV CO., Filling equipment by Combiblock & Ello back Co. And Utilities equipment manufacturing by

different American Co. At 2002

Page 6: Santé Alexandra Overview 02

Santé Overview

7 – All the services and manufacturing workshops for spare parts required are available in this region, as well as most of the raw materials needed for

Products mainly as milk supplies and most importantly with the availability of dairy farms on the Egypt-Alexandria Desert Road

8 – All technical and trained operator and technicians are available in this area with reasonable salaries

9 – The factory premises of the Steel structure Imported From America with 11 meter at the middle and 8 meter at the side allowing to fix racking

system in drive in system to increase storage capacity 10 – The plant has enough space for extension in each section

11 – The Plant could produce all different type of aseptic and Pasteurized milk and Juice with different size and packs

12 – we have space to produce all type of Cheese as white milk, Feta, Mozzarella, Cheddar as well as Laban, Ghee, butter, butter oil and milk powder filling in different size and packs with max capacity 435 ton/day

Page 7: Santé Alexandra Overview 02

Santé Section AreaRemarks % M2 Building Area S

Allow to use 70 % but we have 48% 100% 42 398 Total Plant Area 1

We have big area at second flor 10% 2 067 Administration 2

Easy to increase our capacity 20% 4 383 Processing Halls 3Easy to increase our capacity and add Tetra Pak Filling Lines 11% 2 280 Filling Halls 4

Easy to increase our capacity By Adding New Equipment 10% 2 133 Utility Area 5

Able to increase store capacity by Racking 42% 8 496 Stores – dray, Cold and Freezers 6

At Frist and second floor 5% 1 080 Coli door 7 We still have 22 % to build it up 48% 20 439 Total Area

Building is almost completed – 90 to 95 % excep False Ceilings, some drains, some Auto. Doors

Page 8: Santé Alexandra Overview 02

Santé Planed ProductsDaily Capacity Available Products S Daily Capacity

12000 unit/hr. x 0.25 x 20 = 60 ton/day Aseptic Milk & Juice Products 1 12000 unit/hr. x 0.25 x 20 = 60 ton/day

200 ton/day = 5000 unit/hr. x 2 x 20 125 – 150 – 200 – 250 ML + 2 kg 200 ton/day = 5000 unit/hr. x 2 x 20

ton/day 9000 unit/hr. x 0.5 x 20 = 90 Past. Juices & Laban Raib 2 ton/day 9000 unit/hr. x 0.5 x 20 = 90

9000 unit/hr. x 1 x 20 = 180 ton/day

250 – 500 ML + 1 Kg 9000 unit/hr. x 1 x 20 = 180 ton/day

3000 unit/hr. x 0.1 x 20 = 6 ton/day Cream – 100 Ml 3 3000 unit/hr. x 0.1 x 20 = 6 ton/day

= 3 ton/day Process Cheese different shape 4 = 3 ton/day

ton/day 2500 unit/hr. x 1kg x 14 = 15 Feta Cheese – 250 – 500 Ml 5 ton/day 2500 unit/hr. x 1kg x 14 = 15

500 unit/hr. x 14 = 7 ton/day Mozzarella /Shedder / Romy 6 500 unit/hr. x 14 = 7 ton/day

No processing equipment 200 – 350 g. + 0.5 - 2 Kg

=16 ton/day Butter & Butter oil 7 =16 ton/day

=8 ton/day Filling Milk Powder 330 / 900 / 1800 g. 8 =8 ton/day

=205 to 435 ton/day Min & Max Daily Capacity =205 to 435 ton/day

Page 9: Santé Alexandra Overview 02

Remarks All Processing Equipment to be installed and commissioned

Remarks Capacity UOM Qty Items SAble to add new mixing unit 25000 L / hr. 1 Milk Reception 1

116000 L 3 Silo Tanks 2

Able to Add new Pasteurizer 20000 L / hr. 1 Main Pasteurizer 3Able to add new UHT with Sterile tank 8 - 11 L / hr. 1 UHT 4

4 - 6 L / hr. 1 ESL 5Able to add new raw tanks or pasteurize tanks 30000 L / hr. 4 Aseptic Tanks 6

All Saddar & Mozzarella cheese Processing equipment are MissingAnd totally no spare parts were supplied

1000 L / hr. 1 Cooling Raw Cream 7

1500 L 2 Raw Cream Buffer tank

1 L / hr. 1 Cream

4000 L / hr. 1 Cooling Cream 8

400 – 1000 L / hr. 1 Cream Pasteurizer

7500 L 2 Cream Buffer Tank

No filling machines 3000 L 1 Butter & Butter oil 9

Processing Equipment Capacity

Page 10: Santé Alexandra Overview 02

Filling Equipment CapacityRemarks Capacity UOM P/Hr. UOM Qty Items S

Size- 125 - 150 – 200 - 250 – 500 Ml 42 Ton / day 12000 pc 1 Combibloc # 1 1

Size – 2 Liter 140 Ton / day 5000 pc 1 Combibloc # 2 2

Size- 250 – 500 Ml 90 Ton / day 9000 pc 1 Elopak # 1 3

Size – 1 Liter 180 Ton / day 9000 pc 1 Elopak # 2 4

Products1 – UHT milk

2 – Cream3 – ESL milk

4 – Rayeb milk5 – UHT Juice

6 – all type of Cheese but No Filling

Remarks1 – Elopak need 4 Cap Applicators

2 – Elopak could be installed Free of charge by purchase sleeves

for 4 years3 – Combibloc to be replaced by 3 Tetra pak

filling lines with Millions $ with total support 2 millions$ 4 – able to add Yogurt & Feta filling m/cs

Page 11: Santé Alexandra Overview 02

Utilities Equipment CapacityRemarks Capacity UON Sub-items Utilities

Missing equipment as pumps, filters and pressure tank

300 M3/hr. Water Plant

Missing storage tank 46 M3/min Air station

Need to add another softener 12 Kg/hr. Steam Boiler

Missing Ice bank and control panel

2356 KWH Ice bank Ammonia Plant

Completed 928 TR A/C

Ok -5o C Cold Store

Ok -18o C Freezing Store

To add high voltage breakers and supply Government Power

2 x 1500 KVA Transformer Power Station

Ok 2 x 1000 KVA Generator

Ok 153 M3/hr. Electric Fire Fighting

Ok 153 M3/hr. Diesel

Ok 300 M3/day Sewage Plant

Ok 10 x 15000 L / hr. Milk Tanker

Page 12: Santé Alexandra Overview 02

The Required (Missing ) Equipment •1 – Mozzarella & cheddar Cheese Production Line capacity 5 – 7 ton/d

•     A – plastic bag with size 200 & 350 gram•     B – Block with size 0.5 & 2 kg

•2 – Processing Cheese Production Line – capacity 3 ton/hr. In triangle , • Boxes and Cups

•3 – Cutting m/c and packing for slices processing cheese 10 gram • capacity 1 ton/hr.

•4 – filling m/cs for Feta cheese , Laban and cream in 150 and 500• gram Capacity 2 ton / hr.

•5 – Butter and Butter oil Processing equipment – capacity 2• ton/hr.

•6 – milk powder filling line in bag 330, 900 and 1800 gram – • capacity 1 ton/hr.

Page 13: Santé Alexandra Overview 02

Contact USContact the Consultant of Santé Company

Eng. Reda Ahmed GomaMobil : 002 01111 9233 22

Mail : reda 5 .gomaa @yahoo com

Eng. Tarek Osman AminMobil : 002 0100 5330 115Mail : [email protected]

Page 14: Santé Alexandra Overview 02

التجهيز لمعدات المواد طلب و االصالح تكلفه و مراحلم التعقييم و البستره و التجهيز اقسام المرحله تكلفه

$ االصالحاالصالح تكلفه

بالجنيه 1 Raw Milk Reception & Silo Tanks الثانيه 76,754 1,153,5092 Mixing Equipment الثانيه 29,100 439,7263 Main Pasteurizer الثانيه 34,433 535,3504 Buffer Tanks الثانيه 41,142 617,1355 Juice & Fresh Past. (ESL) & Aseptic Tanks الثانيه 32,009 490,1406 UHT & Aseptic Tanks الثانيه 21,467 332,0107 Raw Cream & Cream Pasteurizer الرابعه 61,699 925,4858 Break fast Cream الرابعه 13,629 205,9639 Feta Cheese Buffer Tanks الثالثه 16,263 243,940

10 Preheater Skid 6.05-6.14 الثالثه 14,155 212,32511 UF Plant Skid 0613.0624 - 3 x 2 ton الثالثه 29,180 434,70012 UF Filters 0610-2 الثالثه 15,000 225,00013 Retentate Heater Skid 0625.0633 الثالثه 10,602 159,03014 Retentate Buffer Tanks الثالثه 23,640 364,600

15Mozzarella / Chidaer Processing Equipment

الخامسه 0 0

16 Laban الثالثه 11,812 177,18017 CIP 1 , 2 and 3 الثانيه 62,323 954,84518 Spare Part Kit for the above الثانيه 24,000 288,000 Total Processing Repaired for APV items 517,208 7,758,938 Total of SPX ( APV ) Equipment including shipment & Clearance 620,650 9,310,726

Page 15: Santé Alexandra Overview 02

م والتغليف التعبئه اقسام المرحله تكلفه $ االصالح

االصالح تكلفهبالجنيه

1 Filling Compiblock filling m/cs # 1 - small sizes الثانيه 300,000 4,800,000

2 Filling Compiblock filling m/cs # 2 - big sizes الثالثه

3 Filling Elopak filling m/cs # 1 - 0.25/0.5 / 1 L الثالثه 25,000 375,000

4 Filling Elopak filling m/cs # 2 - 0.25/0.5 / 1 L الثالثه 25,000 375,000

4 Filling M/Cs for Cheese الثالثه 0 0

5 Filling M/Cs for Yogurt الثالثه 0 0

6 Cream & butter filling m/cs الرابعه 0 0

7 Ghee Processing & filling m/cs الخامسه 0 0

8 Cheese Slicing & Cheader الخامسه 0 0

9 Milk Powder Filling الخامسه 0 0

Total Repair for Filling Sections 350,000 5,550,000

التغليف و التعبئه لمعدات المواد طلب و االصالح تكلفه و مراحل

Page 16: Santé Alexandra Overview 02

م الخدمات اقسام المرحله تكلفه $ االصالح

تكلفه االصالح بالجنيه

1 الكهرباء مصدر الثانيه 125,000 2,000,0002 والثالجات البارد للماء باالمونيا التبريد وحده الثانيه 200,000 3,200,0003 البخار توليد وحده الثانيه 10,000 150,0004 المضغوط الهواء توليد محطه الثانيه 9,375 150,0005 المعالج الماء محطه الثانيه 26,667 400,0006 التكييف وحدات الثانيه 0 0

7الستخراج - ) هام الصناعىى الصرف محطه

التشغيل ( رخصه الثانيه 8,000 120,000

8الستخراج - ) هام الحريق مكافحه محطه

التشغيل ( رخصه الثانيه 6,667 100,000

9معدات و للخدمات المواسير تركيب و توريد

التعبئه و التصنيع الثانيه 65,313 1,045,000

10و للخدمات المواسير عزل وتركيب توريد

التعبئه و التصنيع معدات الثانيه 28,922 462,750

11قبل تراخيصالتشغيل لزوم اخرى وحدات

التشغيل الثانيه

12 Lab. Equipment الثانيه 35,000 525,000 Total Utility Sections 514,943 8,152,750

الخدمات لمعدات المواد طلب و االصالح تكلفه و مراحل

Page 17: Santé Alexandra Overview 02

العرب - برج سانتى لشركه المطلوبه باالعماRل قائمه و جدولم. المجموعه االولى المرحله اعمال مالحظات دفعه تم ما الباقى 1 2 3 4 5 6 7 8

1

ترتيب و المصنع معدات تقييمالقرار اتخاذ و المعدات

تم - النواقص تحديد و الكتالوجات ترتيب التنفيذ تم

100,000

2 صاله كل فى المعدات تحديد و مساحتها و الصاالت ترتيب

3 استكمالها محاوله و المتاحه الرسومات جميع تصوير

4 النواقص و العقد حسب و الرسومات حسب المصنع معدات تحديد

5 المعدات طاقات حساب

6 اماكنها فى المعدات وضع

7 الكالركات تأجير 5,000

8 العقد على الحصول محاوله 10,000

9

للمحافظه الخدمات التركيباتفرص زياده و االصول قيم على

البيع

بخار الخدمات مواسير لحامات و تركيبات

عرضسعر استالم تممن اكثر و 4منذ اشهر

مليون من قيمته زادتالرقم 50و هAذا الى الف

1,600,000

10 هAواء الخدمات مواسير لحامات و تركيبات

11 - امونيا تبريد الخدمات مواسير لحامات و تركيبات

12 ماء الخدمات مواسير لحامات و تركيبات

13الخدمات اقسام نواقص شراء

بارد ماء الخدمات مواسير لحامات و تركيبات 14

15 بارد الماء و االمونيا تبريد و البخار مواسير تركيبات

16 ال + مواسير اصالح التنكات UHT 450,000اصالح 650,000

17

التشغيل تراخيصالمولدات تشغيل من اوفر للمحوالت كهرباء على التعاقد

1,500,000

18 الكاميرات

19 الصناعى الصرف وحده تشغيل و البيئه

Total in L.E. 4,315,000 565,000 3,750,000 197,368 دوالر

م. المجموعه الثانيه المرحله اعمال مالحظات دفعه تم ما الباقى 1 2 3 4 5 6 7 8

1المصنع معدات تركيبات نواقصمن االسبانى APVشراء الشركه او تتراباك او 1,500,000

2 الغسيل اجهزه و العصير لجهاز ميمورى الفالش 50,000

16 التعبئه ماكينات تركيب و توريد فى ) ( قديمه او جديده تتراباك بلوك الكمبيى ماكينات تركيب و توريدتوفير سيتم المستخدم 1,500,000 %50حاله

Total in $ 3,050,000 0 3,050,000