nigel lockyer triumf/ubc srf activities at triumf & pavac canada’s national laboratory for...

19
Nigel Lockyer TRIUMF/UBC SRF Activities at TRIUMF & PAVAC CANADA’S NATIONAL LABORATORY FOR PARTICLE AND NUCLEAR PHYSICS Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada LABORATOIRE NATIONAL CANADIEN POUR LA RECHERCHE EN PHYSIQUE NUCLÉAIRE ET EN PHYSIQUE DES PARTICULES Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada Present Beginning & Future

Upload: prosper-price

Post on 26-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Nigel Lockyer

TRIUMF/UBC

SRF Activities at TRIUMF & PAVAC

CANADA’S NATIONAL LABORATORY FOR PARTICLE AND NUCLEAR PHYSICSOwned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada

LABORATOIRE NATIONAL CANADIEN POUR LA RECHERCHE EN PHYSIQUE NUCLÉAIRE ET EN PHYSIQUE DES PARTICULES  

Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada

Present Beginning & Future

04/19/23

Who is PAVAC? A Canadian Company

located in Richmond B.C.

Products and services in: Electron Beam Welding Precision machining Pulsed Electron Beam

Drilling and Surface-Micro Machining

Pulsed Electron Beam Coating (PEB-PVD)

Rapid Manufacturing (RM) Electron Beam Flue Gas

10,000 + square feet facility at:

12371 Horseshoe WayRichmond, B.C., V7A 4X6

Production/Innovation

April 19, 2023 Lockyer 3

SC-Linac

Refrigerator

SCRF Lab

RFQ

DTL

Mass Separator

Targets

Phase II

April 19, 2023 Lockyer 4

1.0E+07

1.0E+08

1.0E+09

1.0E+10

0 10 20 30 40 50

Ep (MV/m)

Qo

Prototype 1

Prototype 2

7W

Phase-II Cavity Report •Cavities ordered from PAVAC Industries of Richmond BC

•Two prototype cavities tested

• Ep=38MV/m @ 7W

•Twenty production cavities ordered

•fifteen cavities received

April 19, 2023 Lockyer 5

ISAC-II Phase-II Cryomodules

•SCC1 cold tests complete •Checked cavities and rf systems

•Measured static load

•24W @4K compared to 13W for Phase I (heat leak?)

•5ltr/hour LN2

April 19, 2023 Lockyer 6

Installation Schedule•Vault installation has begun

•Beamline removed

•Cryogenics installation nearing completion

•SCC1 to be installed Oct 15

•Will be fully tested after installation

•SCC2/3 – Nov. 15/Dec. 15

•Beam commissioning in Jan.-March 2010

•first experiments April 2010

April 19, 2023 Lockyer 7

ISAC-II Phase-II Summary

• Phase-II linac extension will add 20MV to ISAC-II SC-linac– On schedule for 2009 installation

• Fifteen production cavities received– Cavities for first module meet specification– Some problems with leaks – solution developed

• First cryomodule tested– All systems work; alignment good– Signs of Q-disease in on-line cavities – Direct venting system implemented

• Installation has begun– Installation of all cryomodules by end of 2009– Commissioning in Jan. 2010

April 19, 2023 Lockyer 8

TRIUMF – e-Linac

• Goal: three simultaneous

radioactive beams

• New complimentary

driver (e-linac): electron

driver for Photo-Fission

• New target stations and

mass separators

• New front end and post

accelerators

• Staged installation

Cyclotron

e-linac

ISAC II

ISAC III

ISAC I

New Targets

New MassSeparators

NewFront End

NewAccelerators

Low

Energy

Med

ium

Energy

High

Energy

April 19, 2023 Lockyer 9

• Electron driver for photofission: independent and

complementary to 500 MeV cyclotron

• Composed of five elliptical cavities at 1.3 GHz

• Final specification 50 MeV/10mA ->0.5 MW beam

power, cw – by 2017 (cash flow dependent)

•Staged installation: 30 MeV and 3 mA - 2013

•Injector cryomodule (ICM) - designed, built and

tested as part of the VECC collaboration - 2011

50kW

50kW

5kW

5kW

10MeVGun

Injector-2011 Driver

25MeV

50kW50kW

2013

50kW 50kW 50kW 50kW

50kW50kW

2017

50MeV

E-LINAC

April 19, 2023 Lockyer 10

VECC-ICM

• TRIUMF and VECC are collaborating on a 50MeV high intensity (10mA) cw electron linac for the production of radioactive ions through photofission

• The first stage is the design and construction of two Injector Cryomodules (ICM) to accelerate beams to 10MeV

• Injector module base-line design – Two single cell cavities; independently powered and phased– One multi-cell beta=1 cavity– Operating at 1.3GHz and 2K

• A beam test area is being established at TRIUMF for beam studies in early 2011 – Test high intensity beam dynamics up to 10mA; halo formation – Test beam interaction with cavities and LLRF, HOM excitation,

power coupler operation; 30kW cw operation

April 19, 2023 Lockyer 11

VECC Injector Cryomodule and E-Linac

•Goal is to build two Injector Cryomodules (ICM) one for TRIUMF and one for India by 2012

• cryomodule conceptual design study initiated

April 19, 2023 Lockyer 12

E-Beam test area – 2009-2011

Exclusion zone

x-rays

10m

Gun

Bunch

Injector Module

Diag Station

Cryoline

RF and racks

2K pumps

April 19, 2023 Lockyer 13

•Vacuum vessel and bath insert for single cell test cryostat in hand•Pumps for 2K tested•top plate assembly for initial single cell tests operational•Modification for nine cell tests later this year

2K Cryostat Test

1.3GHz hardware development: cryostat

April 19, 2023 Lockyer 14

R+D with PAVAC• PAVAC to produce two single

cells by end of 2009– Produce and test fixtures,

FNAL/RRCAT dies and Nb– Forming / Welding tests– Cavity production and testing

• Fundamental studies – Weld samples, HAZ analysis,

explore weld parameter space, diagnostics include RRR/visual/beta-NMR

April 19, 2023 Lockyer 15

Bead Pull Measurement Setup

-80 -60 -40 -20 0 20 40 60 800

0.2

0.4

0.6

0.8

1

z (cm)

No

rma

lize

d E

lectr

ic F

ield

•Bead pull apparatus set-up

•Warm tuner being designed in collaboration with U of T

•Other ancillaries in design

•Vertical high pressure water rinse

•String assembly frame

April 19, 2023 Lockyer 16

The Schedule

• Stage 1 – completed by Oct. 2009– define the ICM conceptual design with iterative design cycles of

beam simulations and rf modeling– single cavity prototyping of beta=1 with PAVAC and initializing

1.3GHz test program in ISAC-II

• Stage 2 – completed by Nov. 2010– Design/develop/prepare ICM1

• Prototype and test cavities – July 2010• Design, fabricate and assemble cryomodule• Procure/install rf ancillaries; power couplers, tuners

• Stage 3 – completed by May 2011– Beam test with ICM1 in the ISAC-II vault e-test area

• Stage 4 – completed by Dec. 2011– Fabricate, assemble, test ICM2

April 19, 2023 Lockyer 17

•TRIUMF has a long history of collaborations with CERN both on LHC and ISOLDE

•Canadian contribution to LHC organized through TRIUMF

•TRIUMF – Five year plan proposal includes funds to support Canadian contribution to International Accelerator Projects at ~4M$ and 4FTE’s

•Prototype one SPL 704MHz (beta=0.65 or beta=0.92) cavity with PAVAC

•Qualify PAVAC as a vendor for CERN-SPL

•Contribute to SPL building phase as allowed by funding

TRIUMF/CERN Collaborations

SPL beta=0.65 704MHz cavity

April 19, 2023 Lockyer 18

Summary

• SRF represents a core competency in the lab – New chemical lab expands the capability

• Heavy ion SRF technology centered on ISAC-II Phase-II linac extension– On schedule for 2009 installation

• E-Linac given a timely boost with VECC collaboration– E-Linac Injector beam test by 2011

• International partnerships undertaken to support and augment the existing capability – Aligned with the goals of the next five year plan

April 19, 2023 Lockyer 19

Thanksto Bob Laxdal

for slides

Head of SRF Department

see his talk Berlin SRF