    400kV GIS, Krishnapattnam

    EPC Contractor : BGR Energy Systems Limited.

    Erection Contractor : ALSTOM T&D India Ltd.

    Erection Sub Contractor : RB Electrical & Mechanical Works

    ALSTOM came to Site and Started to work from September 4, 2013 (04.09.2013).

    Works Completed:

    Marking Core Cutting CB Box Shifting Anchor Bolt Fixing Structure Checking CB Erection CT Box Shifting and Testing CB Alignment CT Erection Single phase feeder disconnector Cable Laying Bus duct Enclosure for Common Point Disconnector Erection of Double Bus bar Common Point disconnector Cable tray Erection VT Box Shifting and Testing Line VT Support Structure Erection Bus EMVT Support Structure Erection Erection of BUS EMVT Erection of Bay VT GIB Marking and Core drilling GIB Structure Erection

  • 8/13/2019 GIS Report 1

    2/23

    Marking:

    Marking was started on Sep 4, 2013. All four References are marked with Co

    Ordinates given in the drawings. Centre Point for all bays was marked and Axis for all 3 poles is

    marked with Total Station.

    Work Description Time Taken to complete

    Marking 5 Days

  • 8/13/2019 GIS Report 1

    3/23

    Core Cutting:

    It was started consequently after the completion of Axis Marking. We have to do

    12 no. of holes for 1 breaker. We have 3 breakers for 1 bay.

    Totally we have 9 bays

    1 bay - 3 breakers = 36 no. of holes

    9 bays27 breakers = 324 no. of holes

    M18 Core Cutting bit was used to Core out the Concrete.

    Work Description Time taken to complete

    Core cutting 4 days

  • 8/13/2019 GIS Report 1

    4/23

    CB Box Unpacking and Shifting:

    CB Boxes are started to unpack and shift inside GIS building from 9th

    day

    onwards. All 27 Breakers are unpacked outside GIS and shifted inside.

    Work Description Time taken to complete

    CB Box Shifting 8 days.

  • 8/13/2019 GIS Report 1

    5/23

    Anchor Bolt Fixing:

    Chemical Stud Capsules M16*125 are packed inside the drilled hole to

    strengthen the bolt with concrete and Fastened with Anchor bolts. M16 Anchor bolts are

    fixed for all bases.

    Work Description Time taken to complete

    Anchor Bolt Fixing 3 Days

  • 8/13/2019 GIS Report 1

    6/23

    CB Erection

    A day after Anchor bolt fixing, CB Base Structure Erection is completed within two

    days. CB Positioning is taken place after Base Structure Erection from Bay 1Bay 9. Totally

    we have 27 breakers for 9 bays (3 breakers for Each Bay).

    Work Description Time taken to complete

    Circuit Breaker Erection 4 days

  • 8/13/2019 GIS Report 1

    7/23

    CB Alignment:

    CB Alignment was started after completion of CB Erection. During marking time, we

    have marked the point based on which CB is going to align. CB Alignment tool was fixed at the

    top of Breaker. The Top level of the Breakers for all bay is 2327mm from 0 level.

    Work Description Time taken to complete

    CB Alignment 6 days

  • 8/13/2019 GIS Report 1

    8/23

    Current Transformer Erection:

    CTs are started to erect consequently after the completion of CB Alignment. Here we are

    having four types of CTs based on its core.

    Work Description Time taken to complete

    CT Erection 6 days

  • 8/13/2019 GIS Report 1

    9/23

    Single Feeder Disconnector Erection:

    Erection of Single feeder Disconnector with High speed and low speed earth

    switch was carried out as a parallel activity during the erection of Current Transformer.

    Bay No. of. Cores Core Details

    Line 1 5 Cores F1 F1 N2 F1 F1

    Line 2 5 Cores F1 F1 N2 F1 F1

    GT 1 6 Cores F1 F1 N2 N5 F1 F1

    Bus Reactor 1 5 Cores F1 F1 N4 F3 F3

    Bus Coupler 5 Cores F1 F1 N2 F1 F1

    ST 1 6 Cores F6 F6 N9 N8 F7 F7

    ST 2 6 Cores F6 F6 N9 N8 F7 F7

    GT 2 6 Cores F1 F1 N2 N5 F1 F1

    Bus Reactor 2 5 Cores F1 F1 N4 F3 F3

    Work Description Time taken to complete

    Single Feeder Disconnector 6 days

  • 8/13/2019 GIS Report 1

    10/23

    Cable laying:

    Cable laying was started parallel after the completion of Current transformer and

    Single feeder Disconnector and is progress.

    Bay Total no. of cables Cables Laid

    Bay 1 - Line 1 64 Cables 27 Cables are laid and

    Glanded

    Bay 2 - Line 2 64 Cables 27 Cables are laid and

    Glanded

    Bay 3 - GT 1 64 Cables 30 Cables are laid and

    Glanded

    Bay 4Bus Reactor 1 64 Cables 27 Cables are laid and

    Glanded

    Bay 5 - Bus Coupler 64 Cables 42 Cables are laid and

    Glanded

    Bay 6ST 1 64 Cables 30 Cables are laid and

    Glanded

    Bay 7ST 2 64 Cables 30 Cables are laid and

    Glanded

    Bay 8GT 2 64 Cables 30 Cables are laid and

    Glanded

    Bay 9Bus Reactor 2 64 Cables 27 Cables are laid and

    Glanded

  • 8/13/2019 GIS Report 1

    11/23

    Bus duct Enclosure Erection for Common point:

    Bus duct Enclosures are erected for 8 bays to mount Double Bus bar Disconnector

    on its top. This erection is started after Single feeder disconnector erection.

    Work Description Time taken to complete

    Bus duct Enclosure erection 6 days

  • 8/13/2019 GIS Report 1

    12/23

    Double Bus Bar Common point disconnector

    Double bus bar disconnector erection was completed for Bay 1 and Bay 2.

    Totally we have 24 nos. of Double bus bar common point disconnector. We have erected 6 nos.of Disconnectors.

    Coupling:

    Bus Coupling is done as a parallel activity with the erection of Double bus bar

    disconnetor erection for Bay 1 and bay 2.

    Work Description Time taken to complete

    Erection of Double bus bar disconnector

    and coupling of Bay 1 and Bay 2

    6 days

  • 8/13/2019 GIS Report 1

    13/23

    Cable Tray Fixing:

    It is a parallel activity and started after the erection of Double bus bar

    disconnector and is in progress up to now.

  • 8/13/2019 GIS Report 1

    14/23

    Bus EMVT Support Structure Erection:

    There are 2 sets of Structures are going to be erected in GIS Building for

    Supporting Bus EMVT.

    Main Bus 1

    Bus EMVT 1

    Main Bus 2 - Bus EMVT 2

    Now, we have completed the erection of Bus EMVT 2 Support Structure.

    Line EMVT Support Structure Erection:

    Line EMVT support is fixed in parallel with the Erection of Bus EMVT 2

    Work Description Time taken to complete

    Support Structure Erection for Bus

    EMVT and Line EMVT

    4 days

  • 8/13/2019 GIS Report 1

    15/23

    Erection of Bus EMVT :

    Bus duct Enclosure and Single feeder disconnector with High speed and low

    speed disconnector was erected main bus bar 2 and Bus EMVT is connected to the

    Disconnector.

    Work Description Time taken to complete

    Erection of Bus EMVT with disconnector 3 days

  • 8/13/2019 GIS Report 1

    16/23

    Line VT Erection:

    Line VTs are erected for Bay 1Line 1. The Angle which supports the line VT is

    not found at site. So we constructed Scaffolding arrangement to provide extra support to LineEMVT and it takes half a day time to complete.

    Work Description Time taken to complete

    Erection of Line EMVT 2 days.

  • 8/13/2019 GIS Report 1

    17/23

    GIB Marking and Core Cutting:

    Clearance for GIB marking is given by civil on Nov 5, 2013 and we started

    marking on the same day onwards. Both GIB marking and core cutting are in progress.

  • 8/13/2019 GIS Report 1

    18/23

    GIB Structure Erection:

    Structure for Bay 2 - Line 2 erection is in progress.

  • 8/13/2019 GIS Report 1

    19/23

    Back Charging was planned on January, 2014

    All works should be completed including LV Commissioning on December 31,

    2013. HV Test should start from January 1, 2014.

    Works are completed and has to be completed for Back Charging of 400kV GIS.

    LCC Erection

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Comp Comp Comp Comp Comp Comp Comp

    CB Erection for Bay 1 to Bay 9

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Comp Comp Comp Comp Comp Comp Comp

    CT erection for Bay 1 to Bay 9

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Comp Comp Comp Comp Comp Comp Comp

    Single feeder disconnector with high speed and low speed earth switch

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Comp Comp NA Comp Comp Comp Comp

  • 8/13/2019 GIS Report 1

    20/23

    Double bus bar disconnectorCommon Point

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Coupling

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Comp Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Bay VT

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Comp Not

    Comp

    Not

    Comp

    NA NA Not

    Comp

    Not

    Comp

    Not

    Comp

    NA

    Bus EMVT

    Main Bus 1 Main Bus 2

    Not completed Completed

    GIB Marking and Core cutting

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    NA In

    Progress

    In

    Progress

    NA ---------- In

    Progress

    NA NA NA

  • 8/13/2019 GIS Report 1

    21/23

    GIB Bus duct and Bushing Erection

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    NA Not

    Comp

    Not

    Comp

    NA ---------- Not

    Comp

    NA NA NA

    Single Feeder Disconnector with low speed earth switch

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    NA NA NA NA Not

    Comp

    NA NA NA NA

    Cabling

    Cable laying:

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    In

    progress

    Cable termination

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Earthing

    Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 8 Bay 9

    In

    Progress

    In

    Progress

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

    Not

    Comp

  • 8/13/2019 GIS Report 1

    22/23

    Manpower Requirement:

    Work Front Manpower

    Requirement

    Designation

    GIB Bus Duct Erection 3 Fitter

    Cable laying 2 Electrician, Helper

    Cable termination 3 Electrician

    Double bus bar disconnector

    Erection and Coupling

    4 Fitter

    Marking and Core cutting 2 Fitter, Helper

    Structure Assembly 2 Fitter

    Cable tray, Earthing 2 Electrician, helper

    Totally 18 Manpower are needed. (Excluding supervisor)

    Now we have 9 nos. of manpower from RB Elect and Mech works.

    Supervisor - 1

    Fitter5

    Electrician2

    Helper1

    Still we need 10 more manpower at site.

    Electrician

    3

    Fitter5

    Helper2

  • 8/13/2019 GIS Report 1

    23/23

    Work has been carrying over for 65 days from September 4, 2013

    (Including delays)

    65 Accident free days, Zero Man hour lost. No near miss accident.