The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) Grid Code Awareness Program: Operating Code 2 : Outage And Other Related Planning-Transmission Outage By : OSMAN BIN MOHAMMED KHALID SYSTEM OPERATION DEPARTMENT, TRANSMISSION DIVISION, TNB 20 January 2014

Upload: juzaili-js

Post on 14-May-2017

229 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Grid Code Awareness Program:

Operating Code 2 : Outage And Other

Related Planning-Transmission Outage

By :

OSMAN BIN MOHAMMED KHALID – SYSTEM OPERATION DEPARTMENT, TRANSMISSION DIVISION, TNB

20 January 2014

Page 2: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Operating Codes No.2 (OC2):

Outage and Other Related Planning

2

1. Introduction

2. Objective of OC2

3. Scope

4. ICOMS

5. Procedures

Page 3: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Introduction

3

Page 4: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Objectives of OC2

4

Page 5: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Scope

5

Introduction

Page 6: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Model Used in MGC

6

Introduction

Page 7: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 7

ICOMS-Integrated

Commissioning &

Outage Management

System

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 8: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

ICOMS

8

ICOMS-Integrated Commissioning and Outage Management System

Tool to request, process, approve and produce report for outages.

Developed in-house by Cik Roslina Md Yassin

It has 3 main modules – Transmission Outage, Project Outage and Generator Outage.

Project started in 2009 and 1st version was rolled out on Jan 2010.

2nd Version rolled out on Jun 2010

3rd version rolled out in Sept 2011 and it was a major revamp of ICOMS ver. 2 due to the MGC requirements.

Page 9: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Function of ICOMS

9

Introduction

ICOMS is used for

the following purposes

Outage execution

Outage Review, Coordination,

Rescheduling & Approval Outage Planning

and request

Outage Statistic&

Performance report summary

Page 10: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

ICOMS: Login page

1

0

Page 11: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 1

1

Introduction

PROCEDURES

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 12: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 1

2

Introduction

PLANNED OUTAGE

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 13: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.2. Grid Owner

1

3

Introduction

Page 14: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.2.2 Grid Owner

1

4

Introduction

Page 15: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.3 Network Operators and Distributors

1

5

Introduction

Page 16: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.4 Directly Connected Customers

1

6

Introduction

Page 17: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.5 Interconnected Parties

1

7

Introduction

Page 18: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4 Submission Of Planned Outage Schedules by

Users - summary

1

8

Start of new FY(1st Sept)

Y0

30 Sept Y2-Y5Y1

Under OC2.4.2.2, by end of Sept Grid Owner shall provide the GSO with a “Provisional Transmission Outage Schedule” which covers Year 1 on a daily

basis.

Under OC2.4.2 -2.4.4, by end of Sept Grid Owner, Network Operator & Distributor and Directly Connected

Customer shall provide the GSO with an “Indicative Transmission Outage Schedule” which covers Year 1 to

Year 5.

Note: Each year starts on the 1st Sept.

End of FY(31st Aug)

Page 19: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Planned Outage Request in ICOMS in Y0

1

9

Introduction

Today

Y0

30 Sept

1 Sept 1 Oct 11

ICOMS will be blocked for Planned Outage request for Y1 – Y5 but request for

Unplanned Outage for Y0 is still allowed

Last day to key-in Planned Outage for Y1 –Y5

Start of Y1 End of Y5

First day to key-in Planned Outage for Y1 –Y5

Page 20: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2

0

Operating Codes No.2 (OC2): Outage and Other Related Planning

Operating Codes No.2 (OC2):

Outage and Other Related Planning

PLANNED OUTAGE

-Action by GSO

Page 21: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6 Planning Of Transmission Outage by GSO

2

1

Introduction

starting Y0-1/9

Y0

ending Y0-31/8

31 May 30 Nov

Y2-Y5Y1

2.6.1.6 Final Tr. Sys. Outage Plan

covering Y1 to Y5

2.6.1.3 Draft of Tr. Sys. Outage Plan for Y1-Y5

OC2.6.1 GSO will have to prepare a

Page 22: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Summary of Planned Outage Submission and Planning

2

2

Introduction

1/9

Y0

30/9 31/830/11

Last day to provide the GSO with a “Provisional

Transmission Outage Schedule” which covers Y1 on

a daily basis by Grid Owner

Last day to key in “Indicative Transmission Outage Schedule” for Y1-Y5 by Grid Owner, Network

Operator & Distributor

Note: Each year starts on the 1st Sept.

GSO to come up with draft of Tr. Sys. Out. Plan

for Y1-Y5

GSO to come up with final of Tr. Sys. Out. Plan

for Y1-Y5

31/5Today

Related Parties must start

keying in outage for Y1-Y5

Page 23: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2

3

Introduction

UNPLANNED OUTAGE -

Short Duration

Unplanned Outage

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 24: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2 Operational Planning Timescales for Y0 –

Unplanned Outage

2

4

Page 25: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Notification For Unplanned Outage

2

5

Introduction

Page 26: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Notification For Unplanned Outage-summary

2

6

Introduction1-Outage notification depends on plant/apparatus

and outage duration.

2- Plants - BB or circuits (for 2 or more)-other than BB or circuits (for 2 or more)

3-Outage duration - <1 day- >1 day but <2 days

Page 27: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2 Notification required for Unplanned Outage

2

7

-1 Month

OC2.6.2.7 Min 14 Biz Days Notice

required for outage <1 day for

equipment other than BB & Cct (2

ccts or more)

-4 Months

Intended Outage

Date

-14 Biz

days

OC2.6.2.7 Min 1 month notice required for

outage >1 day but <2days for

equipment other than BB & Cct (2

ccts or more)

OC2.6.2.7 Min 4 months notice

required for BB & Cct (2 ccts or more) for <2 days outage

Page 28: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2

8

Introduction

UNPLANNED OUTAGE -

Other Than Short

Duration Unplanned

Outage

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 29: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.10 Unplanned Outage- other than Short

Duration Unplanned Outage

2

9

Introduction

Page 30: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3

0

OC2.6.2.10 Required Notification for Unplanned

Outage- other than Short Duration Unplanned Outage

-1 Month

OC2.6.2.7 Min 14 Biz Days Notice

required for outage <1 day for

equipment others than BB & Cct (2

ccts or more)

-4 Months

Intended Outage

Date

-14 biz days

OC2.6.2.7 Min 1 month notice required for

outage >1 day but <2days for

equipment others than BB & Cct (2

ccts or more)

OC2.6.2.7 Min 4 months notice

required for BB & Cct (2 ccts or more) for <2 days outage

OC2.6.2.10 Under unavoidable circumstances – Grid Owner must notify the GSO as early as possible for

approval.

Page 31: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3

1

Introduction

Request For Changes Of Outages

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 32: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.2- Request for changes of outages

Page 33: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.2- Request for changes of outages

3

3

Introduction

Y0

No change of outages are allowed by Users

Users can request to change the outage by

writing in to GSO

7 weeks

Page 34: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3

4

Introduction

Programming

Phase

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 35: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase

3

5

IntroductionOC2.7.1 Outage Report

Page 36: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase…cont

3

6

IntroductionOC2.7.4 Outage Confirmation

Page 37: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase-Summary

3

7

Introduction

>Wk -2 Day ahead

OC2.7.5 7 weeks Provisional outage program by 1700 hrs (starting from Wk2 to wk8)

Wk8Wk 1

OC2.7.4 Users submit

notification on confirmation

of outages

OC2.7.5 firmed Day ahead and week ahead outage program

by 1700 hrs

Wk 0(Friday)

Wk7

OC2.7.1 8-weeks outage program

Page 38: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3

8

Introduction

Live Apparatus

Working

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Page 39: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.1 Scheduled Live Apparatus Working

3

9

Introduction

Page 40: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.1 Scheduled Live Apparatus Working…cont

4

0

Last day to notify GSO for all Live Work to be done in

March

Intended live Maintenance Date

1 month

31 Jan 1 March

Page 41: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.2 Unplanned Live Apparatus Working

4

1

Introduction

Page 42: 4. oc2 transmission outage.pdf

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.3 Live Apparatus Working at the request of the

GSO

4

2

Introduction